Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated:
1
00:00:00,000 --> 00:00:16,080
In this tutorial, I will demonstrate how to work with parapets and how to include them
2
00:00:16,080 --> 00:00:20,440
in the Lightning Protection System.
3
00:00:20,440 --> 00:00:26,180
To create a parapet on this roof structure, we first select the structure and then go
4
00:00:26,180 --> 00:00:32,860
to the properties on the left, where we select parapet and yes.
5
00:00:32,860 --> 00:00:37,980
Now a parapet is placed on the roof structure and we can start adapting it according to
6
00:00:37,980 --> 00:00:41,680
our needs.
7
00:00:41,680 --> 00:00:46,900
The entire parapet will adapt to the changes we make if we have selected the complete roof
8
00:00:46,900 --> 00:00:48,459
structure.
9
00:00:48,459 --> 00:00:54,820
However, we can choose to adapt single parts by selecting them individually and either
10
00:00:55,340 --> 00:01:08,019
deleting them by pressing delete or adapting them in the properties window as before.
11
00:01:08,019 --> 00:01:12,540
Before we can integrate the parapet into the Lightning Protection System, we first have
12
00:01:12,540 --> 00:01:16,680
to define the parapet risk areas.
13
00:01:16,680 --> 00:01:23,059
We can do that by using this command here.
14
00:01:23,059 --> 00:01:44,459
For more information, please also see the tutorial on risk areas.
15
00:01:44,459 --> 00:01:52,379
Now we place a regular mesh on the roof surface.
16
00:01:52,379 --> 00:02:00,940
For the additional roof structure, we use a mesh without a ring.
17
00:02:00,940 --> 00:02:08,940
In order to integrate the parapet into the Lightning Protection System, we select it
18
00:02:08,940 --> 00:02:22,539
and change the lightning protection use from unsuitable to the status suitable.
19
00:02:22,539 --> 00:02:28,899
Keeping the control button pressed, we can select the other parts of the parapet and
20
00:02:28,899 --> 00:02:35,740
change the status as well.
21
00:02:35,740 --> 00:02:41,300
Now we can connect the mesh on the roof surface with the parapet by using the command add
22
00:02:41,300 --> 00:02:50,300
mesh down conductor with wire.
23
00:02:50,300 --> 00:02:55,119
Here we can choose where we would like to connect our down conductor, either choosing
24
00:02:55,119 --> 00:03:04,100
the nearest option and connecting directly to the parapet, connecting to the other mesh
25
00:03:04,100 --> 00:03:12,539
or the longest option, a connection to the earthing system.
26
00:03:12,539 --> 00:03:21,839
We can speed up the process by clicking right and choosing closest connection or last connection
27
00:03:21,839 --> 00:03:26,660
or pressing N or L on the keyboard.
28
00:03:26,660 --> 00:03:34,460
Pressing N connects the mesh with a clamp directly to the parapet.
29
00:03:34,460 --> 00:03:47,100
In addition, we can create a down conductor on the outside of the parapet.
30
00:03:47,100 --> 00:03:52,899
Again we can choose where we want to connect our down conductor.
31
00:03:52,899 --> 00:03:58,539
Once integrated into the Lightning Protection System, the parapet is included into the separation
32
00:03:58,539 --> 00:04:08,380
distance calculation and considered for the protection volume.
33
00:04:08,380 --> 00:04:13,899
Lastly we take a look on how to add a mesh cable segment on a parapet.
34
00:04:13,899 --> 00:04:19,420
Therefore we choose the following command and confirm the placement by clicking on the
35
00:04:19,420 --> 00:04:21,459
parapet.
36
00:04:21,459 --> 00:04:32,820
Pressing the spacebar repeats the last command and saves time.
37
00:04:32,820 --> 00:04:38,619
Here as well it makes a difference whether or not the parapet is marked as suited or
38
00:04:38,619 --> 00:04:43,700
unsuited for the Lightning Protection use if we make a connection to the mesh on the
39
00:04:43,700 --> 00:04:48,540
roof structure.
40
00:04:48,540 --> 00:04:54,700
For the suitable parapet, we have the option to connect the mesh with a clamp to the ring
41
00:04:54,700 --> 00:04:57,459
or to the parapet directly.
42
00:04:57,459 --> 00:05:07,500
If we choose the ring, an additional connection to the parapet will be made.
43
00:05:07,500 --> 00:05:20,940
For the unsuitable parapet, the connection can solely be made with the ring on the parapet.
44
00:05:20,940 --> 00:05:25,899
Here no connection to the parapet is possible.
45
00:05:25,899 --> 00:05:30,940
If you later on choose to make changes to the building or the parapet, it's important
46
00:05:30,940 --> 00:05:34,200
to delete the risk areas beforehand.
47
00:05:34,200 --> 00:05:39,559
The parapet will adapt to the new building structure, however, risk areas defined before
48
00:05:39,559 --> 00:05:43,359
the change will not automatically adapt.
49
00:05:43,359 --> 00:05:49,679
You'll find another, more detailed tutorial on risk areas in our e-learning platform.
50
00:05:49,679 --> 00:05:52,519
That's it for this tutorial, thanks for watching.