All language subtitles for 6. When To Break Down Deliverables Further

af Afrikaans
sq Albanian
am Amharic
ar Arabic Download
hy Armenian
az Azerbaijani
eu Basque
be Belarusian
bn Bengali
bs Bosnian
bg Bulgarian
ca Catalan
ceb Cebuano
ny Chichewa
zh-CN Chinese (Simplified)
zh-TW Chinese (Traditional)
co Corsican
hr Croatian
cs Czech
da Danish
nl Dutch
en English
eo Esperanto
et Estonian
tl Filipino
fi Finnish
fr French
fy Frisian
gl Galician
ka Georgian
de German
el Greek
gu Gujarati
ht Haitian Creole
ha Hausa
haw Hawaiian
iw Hebrew
hi Hindi
hmn Hmong
hu Hungarian
is Icelandic
ig Igbo
id Indonesian
ga Irish
it Italian
ja Japanese
jw Javanese
kn Kannada
kk Kazakh
km Khmer
ko Korean
ku Kurdish (Kurmanji)
ky Kyrgyz
lo Lao
la Latin
lv Latvian
lt Lithuanian
lb Luxembourgish
mk Macedonian
mg Malagasy
ms Malay
ml Malayalam
mt Maltese
mi Maori
mr Marathi
mn Mongolian
my Myanmar (Burmese)
ne Nepali
no Norwegian
ps Pashto
fa Persian
pl Polish
pt Portuguese
pa Punjabi
ro Romanian
ru Russian
sm Samoan
gd Scots Gaelic
sr Serbian
st Sesotho
sn Shona
sd Sindhi
si Sinhala
sk Slovak
sl Slovenian
so Somali
es Spanish
su Sundanese
sw Swahili
sv Swedish
tg Tajik
ta Tamil
te Telugu
th Thai
tr Turkish
uk Ukrainian
ur Urdu
uz Uzbek
vi Vietnamese
cy Welsh
xh Xhosa
yi Yiddish
yo Yoruba
zu Zulu
or Odia (Oriya)
rw Kinyarwanda
tk Turkmen
tt Tatar
ug Uyghur
Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated: 1 1 00:00:01,410 --> 00:00:02,690 Sometimes it's not clear 2 2 00:00:02,690 --> 00:00:05,463 how granular you should go with the WBS. 3 3 00:00:06,660 --> 00:00:09,763 When should you break a deliverable into smaller pieces? 4 4 00:00:11,240 --> 00:00:12,780 There are four basic reasons 5 5 00:00:12,780 --> 00:00:15,363 to break down a deliverable into smaller pieces: 6 6 00:00:16,350 --> 00:00:19,713 one, different parts have differing responsibility, 7 7 00:00:20,740 --> 00:00:22,893 two, to separate out waiting time, 8 8 00:00:23,920 --> 00:00:26,110 three, to create interim deliverables 9 9 00:00:27,120 --> 00:00:30,283 and four, the duration is longer than two weeks. 10 10 00:00:31,650 --> 00:00:33,750 Let's look at these situations one by one. 11 11 00:00:34,590 --> 00:00:37,423 First, breaking down by responsibility. 12 12 00:00:38,920 --> 00:00:41,190 If different project team members are responsible 13 13 00:00:41,190 --> 00:00:43,180 for different parts of a deliverable, 14 14 00:00:43,180 --> 00:00:45,760 it should be divided into separate parts 15 15 00:00:45,760 --> 00:00:47,843 each led by a single person. 16 16 00:00:49,340 --> 00:00:53,310 The basic rule is, one person must be accountable 17 17 00:00:53,310 --> 00:00:54,683 for each deliverable. 18 18 00:00:56,610 --> 00:00:59,680 However, this is not needed if several people work 19 19 00:00:59,680 --> 00:01:01,310 on several pieces of the deliverable 20 20 00:01:01,310 --> 00:01:04,520 as part of one functional team where a single lead 21 21 00:01:04,520 --> 00:01:06,763 represents them all at the project level. 22 22 00:01:08,210 --> 00:01:11,290 In this case, you can keep the deliverable as one output 23 23 00:01:11,290 --> 00:01:14,020 with one representative at the project level 24 24 00:01:14,020 --> 00:01:17,130 and that team can then create their own WBS 25 25 00:01:17,130 --> 00:01:19,963 internally at their level for the deliverable. 26 26 00:01:21,340 --> 00:01:22,880 They may have their own precedence diagram 27 27 00:01:22,880 --> 00:01:24,730 for the deliverable as well. 28 28 00:01:24,730 --> 00:01:27,540 The project management process can nest 29 29 00:01:27,540 --> 00:01:29,773 to as many levels as needed. 30 30 00:01:32,150 --> 00:01:35,740 Here's an example, if a conference plan has three sections 31 31 00:01:35,740 --> 00:01:37,450 each led by different people, 32 32 00:01:37,450 --> 00:01:38,510 then you should break up the plan 33 33 00:01:38,510 --> 00:01:40,120 into different deliverables 34 34 00:01:40,120 --> 00:01:41,770 that can be managed individually. 35 35 00:01:42,700 --> 00:01:43,640 You will likely find out 36 36 00:01:43,640 --> 00:01:45,450 when preparing the precedence diagram, 37 37 00:01:45,450 --> 00:01:47,760 that they also have different inputs and outputs 38 38 00:01:47,760 --> 00:01:49,630 and are done at different times. 39 39 00:01:49,630 --> 00:01:52,653 So, separate identification will be needed then as well. 40 40 00:01:55,420 --> 00:01:58,400 Second reason for breaking down a deliverable, 41 41 00:01:58,400 --> 00:01:59,823 breaking out waiting time. 42 42 00:02:01,300 --> 00:02:03,350 Deliverables that contain waiting time 43 43 00:02:03,350 --> 00:02:05,770 for an external reason or event 44 44 00:02:05,770 --> 00:02:07,250 should break the waiting time out 45 45 00:02:07,250 --> 00:02:08,883 into a separate deliverable. 46 46 00:02:10,230 --> 00:02:13,920 For example, for approvals, procurement time, 47 47 00:02:13,920 --> 00:02:16,653 delivery time, paint drying, et cetera. 48 48 00:02:18,220 --> 00:02:20,410 The waiting deliverable has time, 49 49 00:02:20,410 --> 00:02:22,523 but usually no resources or cost. 50 50 00:02:24,580 --> 00:02:26,530 Separate the deliverable into one 51 51 00:02:26,530 --> 00:02:29,020 for what comes before the waiting time, 52 52 00:02:29,020 --> 00:02:31,850 one deliverable for the waiting time itself, 53 53 00:02:31,850 --> 00:02:34,150 and one for what comes after the waiting time. 54 54 00:02:35,910 --> 00:02:38,970 Then it's much easier to plan and manage 55 55 00:02:40,210 --> 00:02:43,410 and it highlights the waiting time on the precedence diagram 56 56 00:02:43,410 --> 00:02:45,910 and Gantt chart so it does not get lost 57 57 00:02:45,910 --> 00:02:47,833 inside a project deliverable. 58 58 00:02:48,714 --> 00:02:50,880 Usually there is nothing you on the project 59 59 00:02:50,880 --> 00:02:52,730 can do about this delay, 60 60 00:02:52,730 --> 00:02:55,713 so you want it to be separate and very visible. 61 61 00:02:58,020 --> 00:02:59,650 Here are some examples, 62 62 00:02:59,650 --> 00:03:02,600 breaking out waiting time for a facilities approval, 63 63 00:03:02,600 --> 00:03:05,640 procurement cycle and waiting for paint to dry 64 64 00:03:06,620 --> 00:03:08,210 shown as they will be flowcharted later 65 65 00:03:08,210 --> 00:03:09,510 on the precedence diagram. 66 66 00:03:10,910 --> 00:03:13,600 This highlights the delays as separate events 67 67 00:03:13,600 --> 00:03:15,383 outside the project's control. 68 68 00:03:17,730 --> 00:03:19,790 Another reason to break down a deliverable 69 69 00:03:19,790 --> 00:03:22,453 is when it has interim deliveries. 70 70 00:03:24,060 --> 00:03:26,030 Often a deliverable cannot be completed 71 71 00:03:26,030 --> 00:03:29,573 until later in a project, but can be started earlier. 72 72 00:03:30,910 --> 00:03:33,070 In this case, it can be very useful 73 73 00:03:33,070 --> 00:03:35,020 to break it into two parts, 74 74 00:03:35,020 --> 00:03:38,330 with the earlier part starting as soon as possible 75 75 00:03:38,330 --> 00:03:39,530 and the final part completing 76 76 00:03:39,530 --> 00:03:41,973 when all the required input is available. 77 77 00:03:43,610 --> 00:03:45,280 This enables clearer presentation 78 78 00:03:45,280 --> 00:03:47,490 of the logic in the precedence diagram 79 79 00:03:48,920 --> 00:03:50,810 and it results in a faster schedule 80 80 00:03:50,810 --> 00:03:53,593 by starting some of the work as early as possible. 81 81 00:03:55,510 --> 00:03:59,140 For example, it's often the case that user documentation 82 82 00:03:59,140 --> 00:04:02,520 can be started as soon as a product design is ready 83 83 00:04:02,520 --> 00:04:05,043 but only finished when the full build is complete. 84 84 00:04:06,530 --> 00:04:09,220 Therefore, as shown in this example, 85 85 00:04:09,220 --> 00:04:10,630 you can break the product deliverable up 86 86 00:04:10,630 --> 00:04:13,940 into separate design and build components 87 87 00:04:13,940 --> 00:04:17,630 and start the user documentation as soon the design is ready 88 88 00:04:17,630 --> 00:04:19,963 and finish it when the build is complete. 89 89 00:04:21,460 --> 00:04:24,240 This results in a more accurate breakout of the project work 90 90 00:04:24,240 --> 00:04:26,060 in the work breakdown structure, 91 91 00:04:26,060 --> 00:04:28,670 a clearer structure in the precedence diagram 92 92 00:04:28,670 --> 00:04:30,853 and a faster schedule in the Gantt chart. 93 93 00:04:33,000 --> 00:04:35,024 This kind of thing often becomes apparent 94 94 00:04:35,024 --> 00:04:38,060 only when creating the precedence diagram. 95 95 00:04:38,060 --> 00:04:40,510 So, keep the trick in mind during that stage, 96 96 00:04:40,510 --> 00:04:43,710 whenever you notice something can start earlier 97 97 00:04:43,710 --> 00:04:45,963 but not be finished until later. 98 98 00:04:49,050 --> 00:04:53,120 The fourth reason to break down deliverables is by duration, 99 99 00:04:53,120 --> 00:04:55,703 but you don't actually put these pieces on the WBS. 100 100 00:04:57,380 --> 00:04:59,130 The project management best practice is 101 101 00:04:59,130 --> 00:05:02,510 that any deliverable longer than two weeks 102 102 00:05:02,510 --> 00:05:06,220 must be decomposed into pieces called "work packages" 103 103 00:05:06,220 --> 00:05:10,263 of maximum two weeks duration to facilitate later tracking. 104 104 00:05:11,650 --> 00:05:16,520 These don't go on the WBS but do go on the Gantt chart, 105 105 00:05:16,520 --> 00:05:19,420 so every month when you status a long deliverable 106 106 00:05:19,420 --> 00:05:21,550 you can tell how it's doing based on the progress 107 107 00:05:21,550 --> 00:05:23,703 of the individual work packages. 108 108 00:05:25,130 --> 00:05:28,020 This avoids the "everything is going great" answer 109 109 00:05:28,020 --> 00:05:30,260 from your leads on longer deliverables 110 110 00:05:30,260 --> 00:05:32,660 until the very end when it's too late to react 111 111 00:05:32,660 --> 00:05:35,280 because you will have internal checkpoints 112 112 00:05:35,280 --> 00:05:38,133 to accurately determine status as you go along. 113 113 00:05:39,910 --> 00:05:42,930 For example, let's say preparation of a document 114 114 00:05:42,930 --> 00:05:44,533 will take more than two weeks. 115 115 00:05:45,800 --> 00:05:48,790 Then, based on the owner's activity breakdown, 116 116 00:05:48,790 --> 00:05:50,910 see the later estimating section, 117 117 00:05:50,910 --> 00:05:52,270 the deliverable could be divided 118 118 00:05:52,270 --> 00:05:56,010 into the following smaller, more manageable work packages 119 119 00:05:56,010 --> 00:05:57,810 that can be individually tracked 120 120 00:05:57,810 --> 00:06:00,060 to obtain accurate status later, 121 121 00:06:00,060 --> 00:06:02,480 thereby ensuring you have early warning 122 122 00:06:02,480 --> 00:06:04,513 if there are any schedule problems. 123 123 00:06:05,920 --> 00:06:07,880 Now when you status the deliverable progress 124 124 00:06:07,880 --> 00:06:09,540 once the project is underway, 125 125 00:06:09,540 --> 00:06:11,870 if any of these work packages are late 126 126 00:06:11,870 --> 00:06:13,590 then you will know the overall schedule 127 127 00:06:13,590 --> 00:06:15,560 has challenges right away 128 128 00:06:15,560 --> 00:06:18,560 and won't be blindsided by learning it only at the very end. 129 129 00:06:19,560 --> 00:06:21,340 What you do about a schedule slip 130 130 00:06:21,340 --> 00:06:23,750 is a completely different question. 131 131 00:06:23,750 --> 00:06:27,403 The first priority is to know as soon as possible. 11543

Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.