Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated:
1
1
00:00:00,721 --> 00:00:02,450
So let's look at some example
2
2
00:00:02,450 --> 00:00:04,290
precedence diagrams.
3
3
00:00:04,290 --> 00:00:07,753
Here's a generic example with deliverables A through J.
4
4
00:00:09,310 --> 00:00:11,670
According to the logic of this project,
5
5
00:00:11,670 --> 00:00:13,820
we can start A and B in parallel
6
6
00:00:13,820 --> 00:00:15,293
immediately after the start.
7
7
00:00:16,510 --> 00:00:20,083
We can start C when both A and B are finished.
8
8
00:00:21,340 --> 00:00:23,040
As soon as B is complete,
9
9
00:00:23,040 --> 00:00:24,193
we can start D.
10
10
00:00:25,070 --> 00:00:26,780
When C is finished,
11
11
00:00:26,780 --> 00:00:28,463
we can start E and F.
12
12
00:00:29,490 --> 00:00:31,830
When both C and D are finished,
13
13
00:00:31,830 --> 00:00:33,053
we can start G.
14
14
00:00:34,090 --> 00:00:35,470
When E is finished,
15
15
00:00:35,470 --> 00:00:36,673
we can start H.
16
16
00:00:37,710 --> 00:00:40,993
We need both F and G finished to start I.
17
17
00:00:42,060 --> 00:00:43,870
When H and I are finished,
18
18
00:00:43,870 --> 00:00:45,760
we can start J.
19
19
00:00:45,760 --> 00:00:46,980
And when J is finished,
20
20
00:00:46,980 --> 00:00:48,380
we've completed the project.
21
21
00:00:50,030 --> 00:00:51,160
As you can see,
22
22
00:00:51,160 --> 00:00:53,740
the precedence diagram is a very natural,
23
23
00:00:53,740 --> 00:00:55,420
intuitive structure,
24
24
00:00:55,420 --> 00:00:57,910
communicating a great deal of information
25
25
00:00:57,910 --> 00:00:59,853
quickly and easily.
26
26
00:01:01,710 --> 00:01:04,483
Here's a precedence diagram for building a shed.
27
27
00:01:05,400 --> 00:01:07,093
We saw a WBS for this earlier.
28
28
00:01:08,360 --> 00:01:10,690
According to the logic of this project,
29
29
00:01:10,690 --> 00:01:13,120
we need the design before we can do anything,
30
30
00:01:13,120 --> 00:01:14,023
which makes sense.
31
31
00:01:15,000 --> 00:01:18,450
With the design in hand we can purchase the materials.
32
32
00:01:18,450 --> 00:01:19,910
Once we have the materials,
33
33
00:01:19,910 --> 00:01:22,350
always assuming we have as many people as we need,
34
34
00:01:22,350 --> 00:01:23,600
we can lay the cement,
35
35
00:01:23,600 --> 00:01:24,770
assemble the walls,
36
36
00:01:24,770 --> 00:01:26,723
and assemble a roof in parallel.
37
37
00:01:28,270 --> 00:01:31,500
Remember we assume infinite resources at this point,
38
38
00:01:31,500 --> 00:01:32,770
since we are just working out
39
39
00:01:32,770 --> 00:01:34,983
the logic of the project itself.
40
40
00:01:35,870 --> 00:01:37,480
We'll take realistic resource constraints
41
41
00:01:37,480 --> 00:01:38,690
into account later
42
42
00:01:38,690 --> 00:01:41,233
but we want to figure out one thing at a time.
43
43
00:01:42,130 --> 00:01:45,340
If it can be done in parallel from a logical standpoint,
44
44
00:01:45,340 --> 00:01:47,630
if we had enough resources,
45
45
00:01:47,630 --> 00:01:49,103
then we diagram it that way.
46
46
00:01:50,870 --> 00:01:52,660
Then once the cement is laid,
47
47
00:01:52,660 --> 00:01:55,060
we have a waiting time for the cement to harden.
48
48
00:01:55,970 --> 00:01:57,880
When the cement has hardened and the walls assembled
49
49
00:01:57,880 --> 00:01:59,333
we can install the walls.
50
50
00:02:00,400 --> 00:02:02,700
Once the walls are installed and the roof assembled
51
51
00:02:02,700 --> 00:02:04,870
we can install the roof.
52
52
00:02:04,870 --> 00:02:08,120
With the roof in place we can install the door.
53
53
00:02:08,120 --> 00:02:10,720
And then with the shed complete we can do a cleanup.
54
54
00:02:12,090 --> 00:02:15,310
The diagram clearly shows the inherent logic
55
55
00:02:15,310 --> 00:02:16,303
of this project.
56
56
00:02:18,810 --> 00:02:21,540
Here's a precedence diagram for making supper.
57
57
00:02:21,540 --> 00:02:23,023
We saw the WBS earlier.
58
58
00:02:24,220 --> 00:02:25,830
According to the logic,
59
59
00:02:25,830 --> 00:02:26,980
first we need the menu.
60
60
00:02:27,920 --> 00:02:29,173
Then we can buy the food.
61
61
00:02:30,100 --> 00:02:33,510
Then assuming we have as many assistants as we need,
62
62
00:02:33,510 --> 00:02:35,780
logically we could prepare the soup,
63
63
00:02:35,780 --> 00:02:36,640
prepare the vegetables,
64
64
00:02:36,640 --> 00:02:37,600
prepare the main course,
65
65
00:02:37,600 --> 00:02:39,100
and set the table in parallel.
66
66
00:02:40,140 --> 00:02:42,550
Once the soup, vegetables, and main course are prepared,
67
67
00:02:42,550 --> 00:02:44,058
they can be cooked.
68
68
00:02:44,058 --> 00:02:46,170
When everything is cooked and the table's set
69
69
00:02:46,170 --> 00:02:47,393
we can serve the food.
70
70
00:02:48,260 --> 00:02:50,250
The meal can then be eaten.
71
71
00:02:50,250 --> 00:02:52,000
Then the table cleared.
72
72
00:02:52,000 --> 00:02:53,450
And then the kitchen cleaned.
73
73
00:02:54,540 --> 00:02:56,890
The diagram simply and clearly shows
74
74
00:02:56,890 --> 00:02:59,663
the inherent logic of preparing the supper.
75
75
00:03:01,607 --> 00:03:04,250
Here's a bit more complicated precedence diagram,
76
76
00:03:04,250 --> 00:03:05,580
for a real project to help
77
77
00:03:05,580 --> 00:03:08,290
the United Nations come up with a single agreed standard
78
78
00:03:08,290 --> 00:03:09,950
for which small arms should be cleared
79
79
00:03:09,950 --> 00:03:11,343
out of high conflict areas.
80
80
00:03:12,500 --> 00:03:14,540
We won't walk through the whole project.
81
81
00:03:14,540 --> 00:03:16,280
But if you review the diagram,
82
82
00:03:16,280 --> 00:03:17,870
the takeaway should be
83
83
00:03:17,870 --> 00:03:21,110
that it displays a tremendous amount of information:
84
84
00:03:21,110 --> 00:03:23,090
the deliverables that need to be produced,
85
85
00:03:23,090 --> 00:03:24,980
the relationships between them,
86
86
00:03:24,980 --> 00:03:28,020
and the various streams that can be done in parallel,
87
87
00:03:28,020 --> 00:03:29,133
all in one page.
88
88
00:03:30,370 --> 00:03:33,140
You can actually see and understand the project
89
89
00:03:33,140 --> 00:03:35,350
from the precedence diagram.
90
90
00:03:35,350 --> 00:03:37,410
The Gantt chart we will produce later,
91
91
00:03:37,410 --> 00:03:40,450
which is built from the precedence diagram,
92
92
00:03:40,450 --> 00:03:42,480
is invaluable for showing how the project maps
93
93
00:03:42,480 --> 00:03:43,890
onto the calendar,
94
94
00:03:43,890 --> 00:03:45,580
and for calculating the critical path
95
95
00:03:45,580 --> 00:03:47,283
and the effect of project delays.
96
96
00:03:48,240 --> 00:03:51,030
But the Gantt chart is a reporting tool,
97
97
00:03:51,030 --> 00:03:53,160
it should not be your main tool
98
98
00:03:53,160 --> 00:03:55,243
for actually managing the project.
99
99
00:03:56,240 --> 00:03:59,160
The precedence diagram is what enables you to see,
100
100
00:03:59,160 --> 00:04:00,190
understand,
101
101
00:04:00,190 --> 00:04:01,330
communicate,
102
102
00:04:01,330 --> 00:04:03,033
and manage the project.
103
103
00:04:04,470 --> 00:04:06,760
A key success imperative:
104
104
00:04:06,760 --> 00:04:09,650
always make sure you produce the precedence diagram
105
105
00:04:09,650 --> 00:04:11,450
with your core project team
106
106
00:04:11,450 --> 00:04:14,583
before taking any further steps in project planning.
107
107
00:04:17,210 --> 00:04:18,630
Here's a precedence diagram
108
108
00:04:18,630 --> 00:04:21,640
for our department process improvement project,
109
109
00:04:21,640 --> 00:04:23,420
to develop more efficient processes
110
110
00:04:23,420 --> 00:04:25,060
and an improved floor plan.
111
111
00:04:25,060 --> 00:04:26,640
A real project I went through once,
112
112
00:04:26,640 --> 00:04:30,080
and that we saw the work breakdown structure for earlier.
113
113
00:04:30,080 --> 00:04:32,330
The team has prepared the precedence diagram
114
114
00:04:32,330 --> 00:04:35,003
and now we can see the logic of the project.
115
115
00:04:35,920 --> 00:04:37,550
We start with a kickoff meeting,
116
116
00:04:37,550 --> 00:04:39,599
a standard best practice.
117
117
00:04:39,599 --> 00:04:41,920
Then in parallel,
118
118
00:04:41,920 --> 00:04:43,060
again assuming at this point
119
119
00:04:43,060 --> 00:04:45,460
we have as many resources as we need,
120
120
00:04:45,460 --> 00:04:47,790
we prepare a draft of the new floor plan,
121
121
00:04:47,790 --> 00:04:50,291
a draft of the new department processes,
122
122
00:04:50,291 --> 00:04:52,893
and a plan for how we are going to train the staff.
123
123
00:04:53,850 --> 00:04:56,220
Once the draft floor plan and processes are complete,
124
124
00:04:56,220 --> 00:04:58,310
we can get some executive feedback
125
125
00:04:58,310 --> 00:05:00,390
and then prepare the second drafts
126
126
00:05:00,390 --> 00:05:03,230
and the first version of the training manual.
127
127
00:05:03,230 --> 00:05:05,950
Once the second draft of the processes are complete
128
128
00:05:05,950 --> 00:05:07,870
we can prepare a one page FAQ
129
129
00:05:07,870 --> 00:05:09,833
and get final executive approval.
130
130
00:05:11,000 --> 00:05:12,440
With the approval in hand,
131
131
00:05:12,440 --> 00:05:15,970
we can prepare the second version of the training manual.
132
132
00:05:15,970 --> 00:05:17,220
We put the risk buffer
133
133
00:05:17,220 --> 00:05:19,790
before the new floor plan implementation,
134
134
00:05:19,790 --> 00:05:23,450
since that is the customer event we want to protect,
135
135
00:05:23,450 --> 00:05:25,600
as we will see further in the risk section.
136
136
00:05:26,880 --> 00:05:29,260
Then when the new floor plan is implemented,
137
137
00:05:29,260 --> 00:05:31,740
we can train the staff in the new processes,
138
138
00:05:31,740 --> 00:05:33,303
and the project is complete.
139
139
00:05:34,800 --> 00:05:36,420
We will use this example project
140
140
00:05:36,420 --> 00:05:39,083
to illustrate the critical path process later.
11471
Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.