Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated:
1
1
00:00:01,470 --> 00:00:03,080
Here's the entire planning stage
2
2
00:00:03,080 --> 00:00:04,563
in a simple flow chart.
3
3
00:00:05,640 --> 00:00:08,130
When you follow this best practice approach,
4
4
00:00:08,130 --> 00:00:12,220
planning is productive and efficient and can almost always
5
5
00:00:12,220 --> 00:00:15,083
be done within five per cent of the project effort.
6
6
00:00:17,290 --> 00:00:20,040
First, the requirements are documented.
7
7
00:00:20,040 --> 00:00:23,160
With all the detail about what the project result needs
8
8
00:00:23,160 --> 00:00:24,260
to meet the objective.
9
9
00:00:25,420 --> 00:00:29,060
Then, the work breakdown structure is prepared.
10
10
00:00:29,060 --> 00:00:31,900
A graphic showing all the deliverables that will be
11
11
00:00:31,900 --> 00:00:33,750
produced during the project,
12
12
00:00:33,750 --> 00:00:36,250
not just for handover to the customer at the end
13
13
00:00:36,250 --> 00:00:38,120
but also including all the things the team
14
14
00:00:38,120 --> 00:00:41,143
has to produce along the way, just to get the project done.
15
15
00:00:42,920 --> 00:00:46,860
With the objective, requirements, and deliverables in hand
16
16
00:00:46,860 --> 00:00:50,363
we have the project scope documented as well as we can.
17
17
00:00:52,100 --> 00:00:55,100
Then we prepare a precedence diagram,
18
18
00:00:55,100 --> 00:00:57,910
a simple and natural flow chart of the deliverables
19
19
00:00:57,910 --> 00:01:01,010
with arrows between them, showing the order they must
20
20
00:01:01,010 --> 00:01:01,843
come together.
21
21
00:01:03,100 --> 00:01:06,130
This diagram is the most human intuitive document we produce
22
22
00:01:06,130 --> 00:01:08,770
during planning and is invaluable
23
23
00:01:08,770 --> 00:01:13,200
for getting the strategy right, communicating the plan to others
24
24
00:01:13,200 --> 00:01:15,123
and managing the project later.
25
25
00:01:16,960 --> 00:01:19,970
After we produce the precedence diagram it's the best time
26
26
00:01:19,970 --> 00:01:22,640
to have the core project team estimate the resources,
27
27
00:01:22,640 --> 00:01:26,360
material, services, time, and cost of each deliverable.
28
28
00:01:26,360 --> 00:01:28,530
Usually with a straight-forward breakdown of
29
29
00:01:28,530 --> 00:01:29,730
the activities required.
30
30
00:01:31,580 --> 00:01:33,810
Given the deliverables documenting the work,
31
31
00:01:33,810 --> 00:01:36,880
the precedence diagram documenting how they come together,
32
32
00:01:36,880 --> 00:01:39,470
and the estimates, we can then put this data
33
33
00:01:39,470 --> 00:01:42,810
into a Gantt chart tool and determine the project schedule
34
34
00:01:42,810 --> 00:01:43,833
and critical path.
35
35
00:01:45,240 --> 00:01:47,890
We can also add up the total project cost,
36
36
00:01:47,890 --> 00:01:51,360
usually broken down by deliverable and often as a graph
37
37
00:01:51,360 --> 00:01:53,103
showing spending across time.
38
38
00:01:54,960 --> 00:01:58,840
In parallel to all this work we prepare a risk register,
39
39
00:01:58,840 --> 00:02:01,880
identifying the risks, shortlisting them,
40
40
00:02:01,880 --> 00:02:04,580
quantifying the probable time and cost,
41
41
00:02:04,580 --> 00:02:08,220
coming up with response plans, and finalizing the risk
42
42
00:02:08,220 --> 00:02:11,410
buffer required thereby providing the project with some
43
43
00:02:11,410 --> 00:02:14,540
extra time and cost to deal with the inevitable problems
44
44
00:02:14,540 --> 00:02:15,633
that will occur.
45
45
00:02:17,550 --> 00:02:22,240
With the scope, schedule, budget, and risks baselined
46
46
00:02:22,240 --> 00:02:24,480
we then put them into a project plan,
47
47
00:02:24,480 --> 00:02:26,690
along with any other items the project needs,
48
48
00:02:26,690 --> 00:02:30,140
such as plans for human resources, communications,
49
49
00:02:30,140 --> 00:02:33,730
procurement or quality, and then brief the sponsor
50
50
00:02:33,730 --> 00:02:35,330
and other relevant stakeholders.
51
51
00:02:36,410 --> 00:02:38,300
At this point there can be a triple constraint
52
52
00:02:38,300 --> 00:02:41,060
rebalancing step required if the stakeholders direct
53
53
00:02:41,060 --> 00:02:44,990
any changes to the plan, in which case we just iterate
54
54
00:02:44,990 --> 00:02:47,450
the planning steps as necessary to make sure
55
55
00:02:47,450 --> 00:02:51,743
the final plan fits their expectations and is feasible.
56
56
00:02:53,930 --> 00:02:56,900
This simple process does more than anything else in
57
57
00:02:56,900 --> 00:02:59,170
the project management life-cycle to maximize
58
58
00:02:59,170 --> 00:03:01,953
the chances our project will be successful.
59
59
00:03:03,050 --> 00:03:07,110
Experience shows that by simply doing these steps
60
60
00:03:07,110 --> 00:03:08,990
the schedule and budget estimates will go from about
61
61
00:03:08,990 --> 00:03:12,400
plus or minus 100% accuracy coming out of initiation
62
62
00:03:12,400 --> 00:03:15,493
to about plus or minus 10% accuracy at the end of planning.
63
63
00:03:17,040 --> 00:03:18,393
And that's the sweet spot.
64
64
00:03:19,310 --> 00:03:21,060
Most sponsors can live with a plan
65
65
00:03:21,060 --> 00:03:24,290
with plus or minus 10% accuracy, which is actually
66
66
00:03:24,290 --> 00:03:26,143
amazingly good before you start.
67
67
00:03:27,340 --> 00:03:30,140
And because of diminishing returns, it would take much more
68
68
00:03:30,140 --> 00:03:32,663
effort and cost to get a more accurate estimate.
69
69
00:03:33,880 --> 00:03:37,170
Spending just 5% of the estimated project effort
70
70
00:03:37,170 --> 00:03:39,869
to get an estimate within plus or minus 10%
71
71
00:03:39,869 --> 00:03:43,473
is the best result for the least work.
72
72
00:03:45,920 --> 00:03:49,303
The gate to execution is then at the end of planning.
73
73
00:03:50,430 --> 00:03:52,800
If you could not meet the schedule and cost constraints
74
74
00:03:52,800 --> 00:03:56,040
given to you in initiation, the end of the planning process
75
75
00:03:56,040 --> 00:03:58,450
provides a coordination point to adjust
76
76
00:03:58,450 --> 00:04:01,860
the triple constraint as needed to provide an acceptable
77
77
00:04:01,860 --> 00:04:04,663
and feasible plan before you start work.
78
78
00:04:06,270 --> 00:04:08,620
You can also always review the plan at any step along
79
79
00:04:08,620 --> 00:04:11,610
the way to get interim direction if it already looks like
80
80
00:04:11,610 --> 00:04:14,150
you cannot meet any time and cost constrains.
81
81
00:04:14,150 --> 00:04:16,450
For example, if after developing the requirements
82
82
00:04:16,450 --> 00:04:18,910
or work breakdown structure it is already obvious
83
83
00:04:18,910 --> 00:04:20,883
the scope is much larger than expected.
84
84
00:04:22,840 --> 00:04:26,570
By the way, the process is exactly the same whether
85
85
00:04:26,570 --> 00:04:29,260
the project is within one organization or
86
86
00:04:29,260 --> 00:04:31,403
a contractual effort between two parties.
87
87
00:04:32,350 --> 00:04:35,560
The only difference is, that for commercial projects
88
88
00:04:35,560 --> 00:04:37,950
the requirements are often prepared by the customer
89
89
00:04:37,950 --> 00:04:40,100
and provided to the planning team as input.
90
90
00:04:41,150 --> 00:04:43,770
But the process is the same either way.
91
91
00:04:43,770 --> 00:04:46,100
And for commercial projects, the project plan
92
92
00:04:46,100 --> 00:04:49,293
is the main document provided in the proposal.
93
93
00:04:51,960 --> 00:04:55,240
Complete common sense, as efficient as trillions of
94
94
00:04:55,240 --> 00:04:57,600
dollars of experience can make it,
95
95
00:04:57,600 --> 00:05:00,643
project planning at its simplest.
8785
Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.