00:00:01,429 --> 00:00:03,524
Now let's look at the practical essentials
2
2
00:00:03,524 --> 00:00:07,530
of preparation of the project schedule.
3
3
00:00:07,530 --> 00:00:09,705
Now that we have all the deliverables,
4
4
00:00:09,705 --> 00:00:12,258
a precedence diagram showing what order they come together
5
5
00:00:12,258 --> 00:00:14,506
and estimates of how long they will take,
6
6
00:00:14,506 --> 00:00:17,010
we can calculate the overall project schedule
7
7
00:00:17,010 --> 00:00:20,093
and the critical path that drives it.
8
8
00:00:20,943 --> 00:00:23,224
The Gantt chart maps the precedence diagram
9
9
00:00:23,224 --> 00:00:26,325
onto the calendar, and is the formal baseline
10
10
00:00:26,325 --> 00:00:28,075
for the project time.
11
11
00:00:29,291 --> 00:00:31,070
For a project of any complexity,
12
12
00:00:31,070 --> 00:00:33,652
we need the help of a Gantt chart application,
13
13
00:00:33,652 --> 00:00:35,868
for example, Microsoft Project,
14
14
00:00:35,868 --> 00:00:38,413
Primavera, or ProjectLibre,
15
15
00:00:38,413 --> 00:00:41,858
to do all the date calculations.
16
16
00:00:41,858 --> 00:00:45,528
We start by entering the project start date,
17
17
00:00:45,528 --> 00:00:47,809
enter the number of hours in the work day
18
18
00:00:47,809 --> 00:00:49,450
individually by resource if they differ
19
19
00:00:49,450 --> 00:00:52,446
for different people or roles,
20
20
00:00:52,446 --> 00:00:56,417
enter the deliverables, their durations from the estimates,
21
21
00:00:56,417 --> 00:01:00,610
and the links between them from the precedence diagram.
22
22
00:01:00,610 --> 00:01:03,657
The tool skips weekends and any specified holidays
23
23
00:01:03,657 --> 00:01:07,472
and lays the deliverables across the calendar.
24
24
00:01:07,472 --> 00:01:09,969
And the tool calculates the critical path
25
25
00:01:09,969 --> 00:01:12,802
that drives the schedule end date.
26
26
00:01:14,182 --> 00:01:17,493
Creating the precedence diagram first and then entering
27
27
00:01:17,493 --> 00:01:19,250
the structure into the Gantt tool
28
28
00:01:19,250 --> 00:01:21,415
makes building a schedule easy
29
29
00:01:21,415 --> 00:01:25,333
and provides several other advantages.
30
30
00:01:25,333 --> 00:01:26,991
The top-level schedule includes
31
31
00:01:26,991 --> 00:01:29,824
only deliverables, not activities.
32
32
00:01:30,879 --> 00:01:33,453
The number of precedence links is minimized
33
33
00:01:33,453 --> 00:01:36,115
to just what is needed.
34
34
00:01:36,115 --> 00:01:39,560
So the Gantt charts ends up being as simple as possible,
35
35
00:01:39,560 --> 00:01:42,677
easily maintainable, and actually useful
36
36
00:01:42,677 --> 00:01:47,094
throughout the project, which is not always the case.
37
37
00:01:47,094 --> 00:01:50,179
Far too often, we dive into the Gantt software
38
38
00:01:50,179 --> 00:01:53,324
without having prepared a precedence diagram first
39
39
00:01:53,324 --> 00:01:55,726
and end up with a schedule that is too complex
40
40
00:01:55,726 --> 00:01:57,763
and hard to maintain.
41
41
00:01:57,763 --> 00:01:59,219
Whenever you make a small update,
42
42
00:01:59,219 --> 00:02:02,131
the changes cascade and are hard to understand.
43
43
00:02:02,131 --> 00:02:05,182
This common complexity problem is solved
44
44
00:02:05,182 --> 00:02:08,765
by developing the precedence diagram first.
45
45
00:02:10,117 --> 00:02:13,608
Also, avoid the built in precedence diagram function
46
46
00:02:13,608 --> 00:02:17,175
in the Gantt software since it redraws the diagram
47
47
00:02:17,175 --> 00:02:19,234
after every update.
48
48
00:02:19,234 --> 00:02:21,658
And instead, maintain the precedence diagram
49
49
00:02:21,658 --> 00:02:24,560
in a separate drawing tool.
50
50
00:02:24,560 --> 00:02:26,853
Usually, you would never keep data in two places
51
51
00:02:26,853 --> 00:02:28,216
if you could avoid it.
52
52
00:02:28,216 --> 00:02:31,002
However, this is an important exception
53
53
00:02:31,002 --> 00:02:33,433
since the need to make updates in two tools
54
54
00:02:33,433 --> 00:02:36,904
is more than outweighed by the complete control you retain
55
55
00:02:36,904 --> 00:02:39,386
over the precedence diagram layout.
56
56
00:02:39,386 --> 00:02:42,463
And the precedence diagram is for human communication,
57
57
00:02:42,463 --> 00:02:45,380
so the layout is really important.