Afrikaans
Akan
Albanian
Amharic
Arabic
Armenian
Azerbaijani
Basque
Belarusian
Bemba
Bengali
Bihari
Bosnian
Breton
Bulgarian
Cambodian
Catalan
Cebuano
Cherokee
Chichewa
Chinese (Simplified)
Chinese (Traditional)
Corsican
Croatian
Czech
Danish
Dutch
English
Esperanto
Estonian
Ewe
Faroese
Filipino
Finnish
French
Frisian
Ga
Galician
Georgian
German
Greek
Guarani
Gujarati
Haitian Creole
Hausa
Hawaiian
Hebrew
Hindi
Hmong
Hungarian
Icelandic
Igbo
Indonesian
Interlingua
Irish
Italian
Japanese
Javanese
Kannada
Kazakh
Kinyarwanda
Kirundi
Kongo
Korean
Krio (Sierra Leone)
Kurdish
Kurdish (SoranĂ®)
Kyrgyz
Laothian
Latin
Latvian
Lingala
Lithuanian
Lozi
Luganda
Luo
Luxembourgish
Macedonian
Malagasy
Malay
Malayalam
Maltese
Maori
Marathi
Mauritian Creole
Moldavian
Mongolian
Myanmar (Burmese)
Montenegrin
Nepali
Nigerian Pidgin
Northern Sotho
Norwegian
Norwegian (Nynorsk)
Occitan
Oriya
Oromo
Pashto
Persian
Polish
Portuguese (Brazil)
Portuguese (Portugal)
Punjabi
Quechua
Romanian
Romansh
Runyakitara
Russian
Samoan
Scots Gaelic
Serbian
Serbo-Croatian
Sesotho
Setswana
Seychellois Creole
Shona
Sindhi
Sinhalese
Slovak
Slovenian
Somali
Spanish
Spanish (Latin American)
Sundanese
Swahili
Swedish
Tajik
Tamil
Tatar
Telugu
Thai
Tigrinya
Tonga
Tshiluba
Tumbuka
Turkish
Turkmen
Twi
Uighur
Ukrainian
Urdu
Uzbek
Vietnamese
Welsh
Wolof
Xhosa
Yiddish
Yoruba
Zulu
Hello, everyone, and welcome to Part 2 of Session 4 in PMGT 823, Project Risk
Management. In Part A, we focused on qualitative risk analysis, how to
and prioritize risks based on expert judgment and experience.
Now, in Part B, we will take things a step further with quantitative risk
analysis. We will explore how to use numerical tools and models to estimate
overall impact of risks on project outcomes. Let's get started.
In this part of the module, we will focus on quantitative risk analysis.
Unlike qualitative analysis, which is based on judgment and prioritization,
approach uses numerical methods to measure overall risk exposure.
We will look at techniques like expected monetary value, decision tree analysis,
and Monte Carlo simulation.
So if you are ready to dive into some numbers, let's go.
Let's return to the full risk management process to see where quantitative risk
analysis fits in.
After planning for risk management, identifying risks, and performing a
qualitative analysis, finally we arrive at step four that is highlighted here.
This step uses numerical methods to estimate the combined effects of the
on overall project objectives.
It is especially helpful when decisions involve significant costs, timelines, or
resource trade -offs similar to the previous part we have two
important questions here what exactly is quantitative data and why is it
important in risk analysis well quantitative data is information you can
count or verify unlike qualitative data like i drink coffee every day
quantitative data tells us exactly how much or how often
For example, I drink four cups of coffee per day or consume 80 grams of coffee.
Both of them are measurable numerical statements.
In the context of project risk, we use this kind of data to analyze the
impact of all risks on project objectives, such as total cost,
variance, or potential delays.
So one more time, what is the real benefit of using quantitative risk
It gives us a clearer picture of our overall risk exposure and it helps us
better informed decisions about the risk responses.
Quantitative risk analysis has two main benefits.
First, it is the only reliable method for assessing the overall level of
risk because it evaluates the combined impact of all risks and uncertainties.
Second, it gives us quantitative data that supports smarter decision -making.
With this data, we can identify which risks deserve more attention and how we
should respond to them, whether it is setting aside more budget, adjusting
schedules, or preparing contingency plans.
But to do this properly, we need a few things.
First, we need high -quality risk data.
we also need a clear baseline for scope, schedule, and cost.
And of course, sometimes we even need specialized software or expert support
build and interpret models.
So when should you actually perform quantitative risk analysis?
It is best suited for large or complex projects, projects with contractual
requirements, or where stakeholders explicitly request it.
You should also consider it when the project is strategically important for
organization or if it is sensitive to delays and overruns.
But even in these cases, you need to check a few things before jumping in.
So say yes to quantitative analysis if you have the necessary tools and data.
You're confident that most key risks have been identified.
You have budget and time for the analysis, and there is low tolerance for
or schedule deviations.
On the other hand, if your data isn't accurate or subjective inputs work just
well for you, then a qualitative approach might be more efficient and
-effective.
Here is the big picture of the quantitative risk analysis process.
On the left, we start with a solid set of inputs.
including the project management plan, risk register, and reliable cost and
schedule estimates.
Without these inputs, the analysis simply won't work.
In the center, we see a range of tools and techniques used to perform the
analysis. These include expert judgment and interviews, visual models like
influence diagrams, and most importantly, simulation tools,
analysis, and decision tree analysis.
We will cover each of these in more detail in upcoming slides.
Now let's look at the main tools and techniques used in quantitative risk
analysis. We usually begin with the expert judgment, which plays a crucial
especially when translating qualitative insights into numeric estimates or when
interpreting complex results.
Next, we have data gathering, often done through interviews with SMEs to get
accurate data on risk probabilities, impact, and dependencies.
Team skills are also vital because they help ensure the group state focus,
minimize conflict, and support consensus building during risk workshops.
Then we come to the representation of uncertainty.
Here, we model uncertainties in things like cost or time using probability
distributions such as triangular, normal, or beta distributions.
And finally, we use data analysis techniques such as simulations to
wide range of possible outcomes, sensitivity analysis to see which
have the biggest impact,
Decision tree analysis to compare different options under uncertainty and
influence diagrams to show how variable and decisions interact visually.
Let's now look at one of the most powerful tools in quantitative risk
that is Monte Carlo simulation.
This method allows us to evaluate how uncertainties in cost or time might
the overall project outcomes.
Here is how it works.
We take input values like cost estimates or activity durations and let the
computer randomly select values from their defined range.
Then we run the model thousands of times and what we get as outputs are things
like histograms showing the frequency of different results such as how often we
finish under budget.
And also S -curves, which gives us the cumulative probability of meeting a
specific cost or a scheduled target.
For example, if your S -curve shows that there is only a 60 % chance of
completing project under $10 million, then it might be a red flag for you.
And also, when we apply simulation to a scheduled risk, we can do a critical
analysis to find out which activities are most likely to appear on the
parts of the project.
And here we have decision tree analysis that is a valuable tool for choosing the
best option when faced multiple project passes.
Each branch of the tree represents a decision or a chance event.
For example, in this case, we are deciding whether to build a new plant or
upgrade the existing one.
The branches continue with possible future events like a strong or weak
And each endpoint shows the resulting outcomes that can be either a gain or
loss. Then to evaluate each branch, we use expected monetary value or EMV,
is the weighted average of all possible outcomes along that path.
For example, in this case, the decision to build a new plant leads to higher
EMV. So that becomes the optimal choice.
Now let's walk through this example.
Imagine you are prime contractor of the project and the contract imposes a $1
,000 penalty per day of late delivery.
Now you have two subcontractor options.
Subcontractor A is the low -cost but risky option.
They offer a cheaper bid, but there is a 50 % chance of a 90 -day delay, which
could cost you $90 ,000 in penalties.
On the other hand, Subcontractor B is more expensive but more reliable.
They have only a 10 % chance of being 30 days late, meaning a smaller penalty
that is $30 ,000.
So how do you decide?
You will use Expected Monetary Value or EMV. For each option, you combine the
original bid with the probability -weighted penalty to get the expected
cut. Let's see how it works.
Now let's look at how we calculate the expected monetary value for each option.
First, we start with subcontractor A that is low but risky choice.
There is a 50 % chance of a $90 ,000 penalty so the total cost could go up to
$200 ,000.
But there is also a 50 % chance of no delay keeping the total cost at $110
As a result, the EMV here that is the weighted average will be $155 ,000 for
this subcontractor.
Next, we evaluate the subcontractor B that is high but reliable one.
With 10 % chance of a 30 -day delay, the total cost could raise up to $170 ,000.
But in 90 % of the time, there is no delay and the cost stays at $140 ,000.
So EMV will be $143 ,000 for this subcontractor.
As a result, although subcontractor B has a higher bid, its lower risk results
in more favorable expected monetary value.
Therefore, subcontractor B is a smarter choice in terms of minimizing expected
cost.
Now let's talk about influence diagrams, which are powerful tools for analyzing
decisions under uncertainty.
They help us visualize relationships between three key elements that are
decisions, like whether or not to invest on certain factors like R &D success
and outcomes such as sales and net profit.
These diagrams uses arrows to show how different elements influence each other.
For example, here we see that our R &D investment decision affects the
likelihood of R &D success, which in turn influence both sales and net
These models often use probability distribution to represent uncertainty
evaluated using simulation tools like Monte Carlo.
FMEA, or failure moods and effects analysis, is a structured approach that
us identify potential failures in a process, product, or system, and
how these failures might affect overall performance.
The key goal of FMEA is to prioritize risk.
There is done using formula called risk priority number or RPN.
RPN multiplies three factors that are severity or how serious the impact of
would be, occurrence or how likely it is to happen, and detection or how likely
we are to notice the risk before it happens.
Each of these factors is scored on a scale from 1 to 10 and by multiplying
scores together we get an RPN between 1 and 1000.
Higher RPN values mean more critical risks which should be addressed first.
Here we apply the FMEA technique to a real world ID project that is the
implementation of a new CRM system.
Imagine during the risk identification phase the team highlighted three major
risks. that are inadequate training for end users, delays in server delivery by
the supplier, and data transfer errors from the legacy system.
For each risk, we assessed the severity, occurrence, and detectability on a
scale from 1 to 10 and then calculated the risk priority number.
The results show that data transfer errors had the highest RPN of 315.
This means it is the most critical risk and should be addressed first in our
mitigation plans.
The other two risks that are inadequate training with an RPN of 210 and server
delay with an RPN of 96 are still important but with lower priority.
One of the most important outcomes of quantitative risk analysis is the risk
report. This report gives us a clear data -driven picture of the project's
overall exposure to risk using both numerical results and narrative
It also helps us update the key project documents including the overall risk
exposure, detailed probabilistic analysis, and a prioritized list of
risks. In addition, we can track trends across analysis results and determine
which risk response are most appropriate.
Before our next session, please make sure to complete the following readings.
Start with chapters 7 and 9 from Kendrick and also review sections 11 .3
.4 from the PEMBOX 6th edition.
To reinforce your learning, please complete the following activities.
First, reply to at least two of your classmates' posts on Discussion Board 2.
Then take Quiz 3, complete Problem 1, and submit Project Milestone 3.
Finally, please take a few minutes to review the Case Study 4.
And that brings us to the end of Part B of our session on Quantitative Risk
Analysis. If you have any questions, please don't hesitate to reach out. You
also email me.
Thank you very much for watching this video
Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.