Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated:
1
00:00:02,060 --> 00:00:04,360
In today's impossible engineering.
2
00:00:04,680 --> 00:00:08,920
If you're a civil engineer and a project
like this doesn't excite you, you're
3
00:00:08,920 --> 00:00:09,960
probably in the wrong game.
4
00:00:10,400 --> 00:00:14,100
The planet's longest triple tower cable
stayed bridge.
5
00:00:14,540 --> 00:00:18,380
There's no doubt the Queen's Ferry
Crossing is a phenomenal bridge and it's
6
00:00:18,380 --> 00:00:19,440
recognised across the world.
7
00:00:20,540 --> 00:00:24,900
It's remarkable engineering, Super Bowls
and the best of British engineering.
8
00:00:25,400 --> 00:00:28,040
Structural engineering on a colossal
scale.
9
00:00:28,760 --> 00:00:31,440
You're talking 40 meters to the bedrock.
10
00:00:31,840 --> 00:00:34,920
You only get one chance to get that
foundation installed.
11
00:00:35,340 --> 00:00:37,900
And the pioneering historic innovations.
12
00:00:38,220 --> 00:00:39,220
So beautiful.
13
00:00:39,640 --> 00:00:41,560
It's a really elegant structure.
14
00:00:42,100 --> 00:00:46,040
So they've made it here to the other
side. Really an extraordinary thing to
15
00:00:47,060 --> 00:00:49,860
That made the impossible possible.
16
00:01:02,140 --> 00:01:06,480
Scotland, a land of imposing peaks and
deep waters.
17
00:01:11,160 --> 00:01:15,760
This unique landscape presents huge
challenges to the team keeping the
18
00:01:15,760 --> 00:01:16,760
connected.
19
00:01:19,020 --> 00:01:23,980
For project manager Lawrence Shackman,
keeping this crucial link up and running
20
00:01:23,980 --> 00:01:27,720
is top priority, and the nation depends
on his success.
21
00:01:30,670 --> 00:01:34,150
The fourth estuary divides Scotland into
two halves.
22
00:01:34,390 --> 00:01:38,550
So from a transport point of view, it's
a huge natural obstacle.
23
00:01:39,690 --> 00:01:44,130
1890, the world famous fourth railway
bridge was built.
24
00:01:44,370 --> 00:01:50,730
And in 1964, the fourth road bridge was
built to allow cars and heavy goods to
25
00:01:50,730 --> 00:01:51,730
cross.
26
00:01:54,150 --> 00:01:57,550
But half a century later, traffic has
more than doubled.
27
00:01:58,700 --> 00:02:01,460
And the road bridge is no longer up to
the job.
28
00:02:04,280 --> 00:02:07,200
A large degree of corrosion was found.
29
00:02:07,560 --> 00:02:11,380
Thousands of the individual strands were
actually found to be broken.
30
00:02:12,040 --> 00:02:17,300
If the bridge continued to decay, it
might need to close to all vehicles by
31
00:02:17,300 --> 00:02:21,900
2021, bringing the central belt of
Scotland to a standstill.
32
00:02:24,360 --> 00:02:28,060
A new bridge was urgently needed to keep
the nation moving.
33
00:02:29,770 --> 00:02:33,470
So engineers have designed a structure
like no other on Earth.
34
00:02:39,970 --> 00:02:42,650
This is the Queensferry Crossing.
35
00:02:45,330 --> 00:02:50,710
A gigantic triple -towered cable -stayed
bridge, the largest in the world.
36
00:02:53,160 --> 00:02:58,180
This undoubtedly has stretched the
limits of what we believe is possible.
37
00:02:58,540 --> 00:03:03,160
It's incredibly light, it's incredibly
slender, and yet it is massive.
38
00:03:04,800 --> 00:03:08,840
The cruise very cross in itself is an
engineering icon which takes its place
39
00:03:08,840 --> 00:03:10,320
beside the other two great bridges.
40
00:03:11,580 --> 00:03:12,920
It's a world beater.
41
00:03:13,180 --> 00:03:16,560
This is the longest two -span cable
structure in the world.
42
00:03:17,100 --> 00:03:19,000
This really is engineering pushed to the
limit.
43
00:03:27,130 --> 00:03:33,950
Standing 180 feet over the water below,
this $1 .8 billion project stretches a
44
00:03:33,950 --> 00:03:36,950
whopping 1 .6 miles from shore to shore.
45
00:03:39,590 --> 00:03:45,990
It's supported by three gigantic towers,
reaching 680 feet high, the equivalent
46
00:03:45,990 --> 00:03:49,850
of 48 double -decker buses stacked one
on top of the other.
47
00:03:51,410 --> 00:03:55,630
The north and south towers sit on record
-breaking underwater concrete
48
00:03:55,630 --> 00:03:56,630
foundations.
49
00:03:57,450 --> 00:04:02,450
The largest reaching 160 feet deep,
dwarfing the Statue of Liberty.
50
00:04:04,030 --> 00:04:11,030
And 122 deck pieces make up the 85 ,000
-ton roadway, secured by
51
00:04:11,030 --> 00:04:13,450
almost 23 ,000 miles of cable.
52
00:04:16,089 --> 00:04:19,910
Hanging over the channel, this giant
marks the dawn of a new age of
53
00:04:19,910 --> 00:04:20,910
superstructure.
54
00:04:24,430 --> 00:04:28,750
So here we are inside the Queen's Free
Crossing, our 2 .7 -kilometer -long
55
00:04:28,750 --> 00:04:31,030
solution to keep Scotland moving.
56
00:04:31,770 --> 00:04:36,870
It's an amazing place to come to and see
such amazing technology and civil
57
00:04:36,870 --> 00:04:39,070
engineering skill come to reality.
58
00:04:45,210 --> 00:04:48,470
But this beast of a bridge isn't just
super long.
59
00:04:50,010 --> 00:04:51,090
See you at the top.
60
00:04:52,390 --> 00:04:58,790
Its three towers are the tallest of any
bridge in the country, soaring
61
00:04:58,790 --> 00:05:01,110
680 feet over the landscape.
62
00:05:02,110 --> 00:05:06,870
The Queensferry Crossing offers an
exceptional bird's -eye view to workers
63
00:05:06,870 --> 00:05:08,050
enough to make the climb.
64
00:05:19,820 --> 00:05:25,920
It's very rare for anyone to come up
here to be able to see out across to
65
00:05:26,220 --> 00:05:28,840
across to Edinburgh, over to the right
there.
66
00:05:29,460 --> 00:05:30,880
It's absolutely stunning.
67
00:05:36,320 --> 00:05:40,800
To construct a record -breaking piece of
engineering, the team faced a list of
68
00:05:40,800 --> 00:05:42,720
seemingly impossible challenges.
69
00:05:45,070 --> 00:05:49,390
How do you erect enormous towers in a
deep and formidable sea channel?
70
00:05:49,990 --> 00:05:54,710
To build your structural foundations,
you have to get down to deep depths of
71
00:05:54,710 --> 00:05:55,710
meters deep.
72
00:05:55,930 --> 00:06:01,150
And reinforce a slender bridge deck to
stay strong and rigid across such a vast
73
00:06:01,150 --> 00:06:02,150
span.
74
00:06:03,670 --> 00:06:08,290
There's heavy traffic that needs to be
supported, and this creates huge
75
00:06:08,290 --> 00:06:13,010
imbalances that really challenges the
performance of the deck itself.
76
00:06:13,930 --> 00:06:18,630
And where vehicles on the old bridge had
no protection from high winds, how will
77
00:06:18,630 --> 00:06:20,630
the new crossing take on Mother Nature?
78
00:06:21,630 --> 00:06:25,750
The wind speeds can get up to 120 miles
an hour. That puts road users at risk.
79
00:06:30,050 --> 00:06:35,210
To achieve this, engineers must draw
inspiration from the pioneers of the
80
00:06:38,610 --> 00:06:42,350
The first challenge fell to engineer
Douglas Halliday and his team.
81
00:06:42,910 --> 00:06:46,470
who needed to create a solid foothold at
the bottom of the sea.
82
00:06:49,510 --> 00:06:52,290
Want to build your foundations is a
major undertaking.
83
00:06:52,610 --> 00:06:54,610
This is a major channel. It's a major
estuary.
84
00:06:54,890 --> 00:06:56,850
It's great. It's all sorts of problems.
85
00:06:57,690 --> 00:07:01,730
You're talking 40 meters plus below
water level to the bedrock.
86
00:07:01,990 --> 00:07:05,230
You only get one chance, really, to get
that foundation installed.
87
00:07:06,610 --> 00:07:10,270
Where deepwater foundations are
fundamental to the superstructure.
88
00:07:11,240 --> 00:07:13,260
the team had to take the plunge.
89
00:07:15,240 --> 00:07:19,680
The South Tower and the North Tower
foundations were constructed within
90
00:07:19,680 --> 00:07:26,120
because of the depth, twin -walled steel
tubes, open -ended, top and bottom, and
91
00:07:26,120 --> 00:07:31,300
gradually we just tilted and shoot that
caisson down to bedrock level,
92
00:07:31,560 --> 00:07:36,580
constantly monitoring the position of
the caisson using GPS techniques.
93
00:07:36,840 --> 00:07:38,440
That was an immense achievement.
94
00:07:39,400 --> 00:07:44,160
With the caissons placed with extreme
precision, pumps completely emptied them
95
00:07:44,160 --> 00:07:45,160
of seawater.
96
00:07:48,040 --> 00:07:54,200
And in an unparalleled 15 -day
operation, running 24 hours a day, the
97
00:07:54,200 --> 00:07:59,000
executed the planet's longest -ever
continuous concrete pour below water
98
00:08:01,300 --> 00:08:05,260
It's quite hard to appreciate the full
magnitude of the scale of what's below
99
00:08:05,260 --> 00:08:06,260
the water here.
100
00:08:08,040 --> 00:08:12,620
Just to give you an idea, you've got
roughly 50 meters of tower on display
101
00:08:13,900 --> 00:08:17,940
Below water, you've probably got another
40 meters before you hit the bedrock.
102
00:08:18,120 --> 00:08:21,160
So that's the sort of scale we're
talking about below the water here.
103
00:08:21,760 --> 00:08:23,860
It is an amazing engineering
achievement.
104
00:08:26,020 --> 00:08:31,240
But for the Central Tower Foundation,
engineers saw an opportunity that they
105
00:08:31,240 --> 00:08:32,240
couldn't pass up.
106
00:08:32,970 --> 00:08:37,750
This location was chosen because of the
existence of a dollarite, very, very
107
00:08:37,750 --> 00:08:41,710
hard volcanic rock, rocky outcrop in the
middle of the front of the floor. So it
108
00:08:41,710 --> 00:08:46,710
was ideal to set the central tower
foundation on because of the immense
109
00:08:46,710 --> 00:08:47,950
that that rock is going to take.
110
00:08:48,730 --> 00:08:51,130
To prepare the super tough rock,
111
00:08:52,210 --> 00:08:58,550
the team blasted away roughly 175 ,000
cubic feet of material with powerful
112
00:08:58,550 --> 00:08:59,550
explosives.
113
00:09:01,200 --> 00:09:05,400
and shaped it to hold 140 ,000 cubic
feet of concrete.
114
00:09:06,160 --> 00:09:12,300
So there's a robust reinforced concrete
base below that tower, on which we've
115
00:09:12,300 --> 00:09:16,140
placed some decorative rock effectively
to try and create the illusion that the
116
00:09:16,140 --> 00:09:18,300
tower is coming straight out of the
rock.
117
00:09:20,440 --> 00:09:25,200
With the rock -solid foundation in
place, teams set to work erecting the
118
00:09:25,200 --> 00:09:27,640
country's three tallest ever bridge
towers.
119
00:09:32,460 --> 00:09:37,200
Over 800 ,000 cubic feet of concrete was
poured in incremental stages,
120
00:09:37,920 --> 00:09:43,360
pumped all the way from barges on the
water up to the tower's 680 -foot -high
121
00:09:43,360 --> 00:09:44,360
apex.
122
00:09:45,860 --> 00:09:51,680
And after almost two years of
perseverance through moody Scottish
123
00:09:51,680 --> 00:09:55,200
towers were finished and finally ready
to support a roadway.
124
00:10:02,220 --> 00:10:06,960
But to reach them from the shore,
engineer Jill Baker and the team faced
125
00:10:06,960 --> 00:10:07,960
obstacle.
126
00:10:08,580 --> 00:10:12,980
There were many challenges to
constructing both the north and the
127
00:10:12,980 --> 00:10:18,160
viaducts. And this very steep sloping
ground made it very unsuitable for heavy
128
00:10:18,160 --> 00:10:24,500
craneage. You need a good, secure,
stable, level space for any use of
129
00:10:28,740 --> 00:10:33,280
Without traditional cranes, the team
will need to draw inspiration from the
130
00:10:33,280 --> 00:10:36,860
pioneers of the path to link the record
-breaking towers.
131
00:10:38,420 --> 00:10:40,480
So they've made it here to the other
side.
132
00:10:42,960 --> 00:10:48,620
This is the Queensferry Crossing.
133
00:10:51,520 --> 00:10:56,120
A record -breaking structure the likes
of which the world has never seen
134
00:10:58,710 --> 00:11:02,750
38 ,000 tons of steel has gone into the
bridge deck alone.
135
00:11:03,510 --> 00:11:07,790
The approximate weight of 200 747
passenger jets.
136
00:11:08,990 --> 00:11:14,450
Every day it carries 80 ,000 cars and
heavy goods vehicles, keeping Scotland
137
00:11:14,450 --> 00:11:15,770
the move 24 -7.
138
00:11:17,730 --> 00:11:22,050
But the banks on either side of the 4th
estuary are not compatible with
139
00:11:22,050 --> 00:11:23,490
traditional crane construction.
140
00:11:24,940 --> 00:11:29,600
To find a way to erect their bridge
towers in this challenging location, the
141
00:11:29,600 --> 00:11:31,980
team is looking to the engineers of the
past.
142
00:11:39,400 --> 00:11:42,420
At a South Yorkshire limestone quarry in
the UK,
143
00:11:43,140 --> 00:11:50,140
engineer Luke Bisbee is on the hunt for
an innovation that
144
00:11:50,140 --> 00:11:51,660
changed the course of history.
145
00:11:55,090 --> 00:11:59,130
During World War II, Hitler ordered his
troops to start destroying bridges. And
146
00:11:59,130 --> 00:12:01,970
this was a very clever idea to slow down
the Allied forces.
147
00:12:02,330 --> 00:12:06,150
No bridge means the Allied forces have a
massive detour in order to get where
148
00:12:06,150 --> 00:12:07,150
they're going.
149
00:12:07,270 --> 00:12:11,230
To fight back, the Allies needed to
rebuild bridges and fast.
150
00:12:14,810 --> 00:12:19,110
Knowing that bridges were vital to the
war effort, British engineer Sir Donald
151
00:12:19,110 --> 00:12:22,310
Bailey started sketching up an idea on
the back of an envelope.
152
00:12:24,750 --> 00:12:28,870
In 1940, he developed a concept that
changed the war.
153
00:12:35,470 --> 00:12:37,810
This is a Bailey Bridge.
154
00:12:40,590 --> 00:12:43,830
Wow, so this is the modern version of
the Bailey Bridge.
155
00:12:44,110 --> 00:12:47,870
A portable, quick -to -build bridge that
can be adapted to suit just about any
156
00:12:47,870 --> 00:12:53,810
location. And this one here is spanning
42 meters from side to side over a drop
157
00:12:53,810 --> 00:12:54,870
of about 20 meters.
158
00:12:55,490 --> 00:12:56,510
Pretty spectacular.
159
00:13:00,190 --> 00:13:02,530
Over 80 years after conception,
160
00:13:03,350 --> 00:13:07,750
Bailey's flat -packed bridge design is
being erected to connect two important
161
00:13:07,750 --> 00:13:12,250
areas of this quarry without the
assistance of heavy lifting crane.
162
00:13:18,030 --> 00:13:22,690
So you can see here, this is one panel
section of the bridge from here over to
163
00:13:22,690 --> 00:13:27,290
there. By adding more panels along the
bridge, you can adapt this for your
164
00:13:27,290 --> 00:13:28,290
particular location.
165
00:13:30,710 --> 00:13:33,670
No single piece weighed more than 570
pounds.
166
00:13:33,930 --> 00:13:38,230
And this meant that any piece could be
lifted by six soldiers, which crucially
167
00:13:38,230 --> 00:13:42,090
meant that no cranes or heavy lifting
was required, which is absolutely
168
00:13:42,090 --> 00:13:43,510
in a combat situation.
169
00:13:44,650 --> 00:13:49,090
Super light bridge sections could be
easily transported to the battlefield
170
00:13:49,090 --> 00:13:50,150
assembled by hand.
171
00:13:51,410 --> 00:13:55,210
And its modular design meant that the
Bailey Bridge could be progressively
172
00:13:55,210 --> 00:13:57,710
launched, growing as it inches forward.
173
00:14:01,490 --> 00:14:03,310
Okay, boys, pull the spikes.
174
00:14:04,790 --> 00:14:09,210
But how were Bailey Bridges built across
rivers and ravines without a crane?
175
00:14:09,910 --> 00:14:11,590
Nice and slowly, if you please.
176
00:14:19,030 --> 00:14:23,010
By counterweighting one end of the
structure, it could be pushed out and
177
00:14:23,010 --> 00:14:24,010
the valley.
178
00:14:24,870 --> 00:14:28,730
The key thing about the Bailey Bridge is
that you can launch it from one side.
179
00:14:35,770 --> 00:14:37,510
It's absolutely extraordinary.
180
00:14:38,330 --> 00:14:43,230
104 tons of bridge just sliding past me
on some rollers. Unbelievable.
181
00:14:44,170 --> 00:14:46,510
But without supports to hold up the
span.
182
00:14:46,760 --> 00:14:48,740
there's an additional challenge to
overcome.
183
00:14:52,080 --> 00:14:55,540
A key problem that you have is that the
front of the bridge is going to want to
184
00:14:55,540 --> 00:14:57,460
angle down under the weight of the
structure.
185
00:14:57,780 --> 00:15:01,480
And so it's really important when you're
launching a bridge in this way to keep
186
00:15:01,480 --> 00:15:05,100
the nose of the bridge up, because
otherwise, as you're pushing it across,
187
00:15:05,100 --> 00:15:06,620
might just bump into the other side.
188
00:15:08,220 --> 00:15:12,120
But Bailey had thought of everything and
angled the front section of his bridge
189
00:15:12,120 --> 00:15:15,240
up to ensure it cleared the bank on the
other side.
190
00:15:20,400 --> 00:15:21,400
Here it comes.
191
00:15:21,860 --> 00:15:24,220
I think this is actually a pretty
critical moment right here.
192
00:15:26,660 --> 00:15:28,560
So they've made it here to the other
side.
193
00:15:31,860 --> 00:15:32,960
They've actually done it.
194
00:15:36,840 --> 00:15:38,600
Really an extraordinary thing to see.
195
00:15:40,880 --> 00:15:45,720
By the end of the war, around 700 ,000
Bailey Bridge panels had been made.
196
00:15:47,230 --> 00:15:51,650
Both British and American generals have
praised the Bailey Bridge as one of the
197
00:15:51,650 --> 00:15:54,010
key factors leading to an Allied
victory.
198
00:15:58,090 --> 00:16:01,950
With his ingenious yet simple design for
a bridge that could be built and
199
00:16:01,950 --> 00:16:06,610
launched by hand and without a crane,
Donald Bailey had helped bring an end to
200
00:16:06,610 --> 00:16:07,610
World War II.
201
00:16:08,520 --> 00:16:12,800
This is an amazing thing. To see this
technology still doing its job so many
202
00:16:12,800 --> 00:16:16,280
years later is really wonderful and a
real testament to the innovation that
203
00:16:16,280 --> 00:16:17,280
involved.
204
00:16:28,400 --> 00:16:33,380
In Scotland, engineers have taken the
same concept and supersized it.
205
00:16:34,600 --> 00:16:39,460
The only way to the Queensferry
Crossing's towers from the shore is with
206
00:16:39,460 --> 00:16:42,420
gigantic, progressively launched
Approach Viaduct.
207
00:16:46,000 --> 00:16:51,660
The chosen solution for the South
Approach Viaduct was a progressive
208
00:16:52,480 --> 00:16:54,560
It was launched span by span.
209
00:16:55,320 --> 00:16:59,760
We achieved this launch, which goes out
virtually half a kilometer to where the
210
00:16:59,760 --> 00:17:00,780
cable stay bridge is.
211
00:17:01,080 --> 00:17:03,160
This eliminated the need for any large
cranes.
212
00:17:08,970 --> 00:17:13,849
Where heavy lifting cranes can't be
erected on the steep slopes, six
213
00:17:13,849 --> 00:17:16,730
piers were evenly arranged out towards
the towers.
214
00:17:18,310 --> 00:17:23,050
The team then inched the bridge deck
forward from the abutment piece by
215
00:17:23,369 --> 00:17:28,670
Each time they reached a pier, a new
section was welded to the back, and the
216
00:17:28,670 --> 00:17:33,150
process would repeat until the viaduct
reached almost half a mile out over the
217
00:17:33,150 --> 00:17:34,150
supporting piers.
218
00:17:36,840 --> 00:17:41,200
And just like the Bailey Bridge, the
overhanging deck had to fight gravity.
219
00:17:42,640 --> 00:17:47,160
As the launch progressed, the tip would
want to deflect under its own weight.
220
00:17:48,180 --> 00:17:53,640
This could have been catastrophe if the
tip actually put load, lateral load,
221
00:17:53,720 --> 00:17:54,720
into these piers.
222
00:17:54,960 --> 00:18:00,620
But we had this king post system in
place, a 35 -meter vertical temporary
223
00:18:00,720 --> 00:18:03,340
and there was a strand system coming
over the king post.
224
00:18:03,640 --> 00:18:07,780
and connected to the tip. As these
strands were tensioned, it would lift
225
00:18:07,780 --> 00:18:09,000
and land it on the pier.
226
00:18:10,380 --> 00:18:12,480
It was a pretty remarkable solution.
227
00:18:14,360 --> 00:18:19,240
But where the North Shore slopes are
even steeper, a more extreme approach
228
00:18:19,240 --> 00:18:20,240
needed.
229
00:18:20,540 --> 00:18:25,180
We would have had to excavate a lot more
ground to assemble the girders at the
230
00:18:25,180 --> 00:18:26,680
right profile for the launch.
231
00:18:26,940 --> 00:18:30,080
So the solution here, rather than being
a progressive launch...
232
00:18:30,350 --> 00:18:34,950
The whole structure, 220 meters, was
assembled as one unit, and then it was
233
00:18:34,950 --> 00:18:37,170
launched in one massive launch.
234
00:18:39,850 --> 00:18:45,030
In a single daring maneuver, engineers
pushed the enormous deck span directly
235
00:18:45,030 --> 00:18:50,990
forward and then pivoted over the
supporting pier to tilt upwards and
236
00:18:50,990 --> 00:18:52,270
the rest of the bridge structure.
237
00:19:00,430 --> 00:19:03,890
It was a big relief when we finally
achieved our desired solution.
238
00:19:04,670 --> 00:19:09,930
I don't know of another launch so large,
6 ,000 tons, being pushed out 220
239
00:19:09,930 --> 00:19:12,390
meters, and then having to do this
pivot.
240
00:19:12,670 --> 00:19:17,170
It was remarkable engineering, super
balls, and it's the best of British
241
00:19:17,170 --> 00:19:18,170
engineering.
242
00:19:26,350 --> 00:19:31,280
But with the approach viaducts in place,
It takes more impossible engineering to
243
00:19:31,280 --> 00:19:33,040
join this megastructure together.
244
00:19:33,920 --> 00:19:39,340
The sort of equipment that you need to
build those units are very special
245
00:19:39,340 --> 00:19:40,340
of equipment.
246
00:19:40,820 --> 00:19:45,240
For a solution, engineers must turn to
the great innovators of the past.
247
00:19:45,820 --> 00:19:48,980
You really get a sense of how long this
bridge is.
248
00:19:49,780 --> 00:19:52,200
We can barely see the other end of it.
249
00:20:00,170 --> 00:20:03,850
In Scotland is a superstructure that
defies the impossible.
250
00:20:07,470 --> 00:20:10,490
In a bid to keep the country connected.
251
00:20:12,350 --> 00:20:18,990
The triple -towered Queensferry Crossing
boasts two enormous 2 ,100 -foot spans.
252
00:20:19,990 --> 00:20:25,050
Over 2 ,500 concrete pours executed
across the project.
253
00:20:25,470 --> 00:20:30,950
pumped a staggering 165 ,000 tons of
concrete into the megastructure.
254
00:20:34,070 --> 00:20:38,850
But before vehicles can cross the
channel, they're going to need a road to
255
00:20:38,850 --> 00:20:39,850
on.
256
00:20:40,370 --> 00:20:45,010
Engineer Richard Hornby oversaw the
operations behind crucial deck segment
257
00:20:45,010 --> 00:20:46,010
construction.
258
00:20:49,520 --> 00:20:52,600
This is a port here.
259
00:20:52,860 --> 00:20:56,460
This was the sort of the marine nerve
center for the project.
260
00:20:59,640 --> 00:21:03,060
For the deck itself, the deal was made
in China.
261
00:21:03,380 --> 00:21:07,720
The units were delivered on four ships
on this quayside here.
262
00:21:10,920 --> 00:21:17,440
122 steel deck sections, each weighing
up to 400 tons, were offloaded by an 1
263
00:21:17,440 --> 00:21:18,960
,100 -ton megacrane.
264
00:21:20,430 --> 00:21:25,710
and taken one by one to the concrete
casting shed to be capped by another 300
265
00:21:25,710 --> 00:21:27,630
tons of reinforced concrete.
266
00:21:32,590 --> 00:21:36,950
But to get these super heavy deck pieces
from the dockyard up onto the
267
00:21:36,950 --> 00:21:39,510
megastructure would be a battle with the
elements.
268
00:21:40,910 --> 00:21:44,130
The conditions on the east coast of
Scotland are not benign.
269
00:21:46,520 --> 00:21:51,380
There's long periods of strong wind.
There is a strong tidal flow.
270
00:21:53,640 --> 00:21:57,100
The sort of equipment that you need are
very special pieces of equipment.
271
00:21:57,560 --> 00:22:01,940
Big plate and crane that are stable in
essentially open water.
272
00:22:03,940 --> 00:22:08,760
But where the water depth varies, a one
-size -fits -all solution just won't cut
273
00:22:08,760 --> 00:22:09,760
it.
274
00:22:11,530 --> 00:22:16,470
The floating cranes need significant
depth of water, and towards the ends of
275
00:22:16,470 --> 00:22:20,270
bridge, there really isn't enough water
depth, and so you might well have had to
276
00:22:20,270 --> 00:22:25,170
have two different lifting systems, one
using the floating crane and one to deal
277
00:22:25,170 --> 00:22:27,270
with the areas where the floating crane
couldn't get to.
278
00:22:28,610 --> 00:22:34,570
In a varied seascape where multiple
systems would be needed, floating cranes
279
00:22:34,570 --> 00:22:35,570
not an option.
280
00:22:35,970 --> 00:22:39,770
The team must find another way to
install heavy deck segments.
281
00:22:39,980 --> 00:22:42,140
by turning to history's innovators.
282
00:22:52,420 --> 00:22:57,620
In the rugged landscape of Lethbridge,
Alberta... Watch your steps.
283
00:22:58,880 --> 00:23:03,900
Mechanical engineer Agnes D 'Entremont
is exploring the deep ravines that kept
284
00:23:03,900 --> 00:23:05,240
southern Canada divided.
285
00:23:06,770 --> 00:23:11,870
Connections by rail within southwestern
Canada were really important at the end
286
00:23:11,870 --> 00:23:16,330
of the 19th century to get southern
Alberta coal into British Columbia.
287
00:23:16,690 --> 00:23:20,570
But they had to deal with terrain like
this, deep ravines.
288
00:23:20,890 --> 00:23:27,150
A real solution was needed for the
railways to cross these dangerous river
289
00:23:27,150 --> 00:23:28,150
valleys.
290
00:23:30,640 --> 00:23:34,960
Tasked with making this dream a reality
was Assistant Chief of Engineering at
291
00:23:34,960 --> 00:23:37,960
Canadian Pacific Railway, John Edward
Schwitzer.
292
00:23:41,400 --> 00:23:47,280
In 1909, he unveiled a revolutionary
structure that changed the world of
293
00:23:47,280 --> 00:23:48,280
engineering.
294
00:23:49,820 --> 00:23:51,860
The Lethbridge Viaduct.
295
00:23:55,800 --> 00:23:57,540
Wow, it's incredible!
296
00:24:01,640 --> 00:24:07,900
Almost a mile long and 315 feet high,
it's the longest and highest steel
297
00:24:07,900 --> 00:24:09,520
railroad trestle in the world.
298
00:24:15,520 --> 00:24:20,300
So this is it. This is Switzerland's
solution to keeping southwest Canada
299
00:24:20,300 --> 00:24:26,220
connected. The Lethbridge Viaduct, which
you can see above me, spans this entire
300
00:24:26,220 --> 00:24:28,820
valley but keeps the rails almost level.
301
00:24:30,800 --> 00:24:34,640
At this point, the bridge is nearly 100
meters above us.
302
00:24:35,060 --> 00:24:40,240
Imagine having to lift massive steel
beams that high in the air to construct
303
00:24:40,240 --> 00:24:45,200
this bridge. Having a crane down here
would be impractical. Not only because
304
00:24:45,200 --> 00:24:48,480
terrain is rugged and there's a river,
there are varying land heights.
305
00:24:50,120 --> 00:24:54,660
Just like in Scotland, the varied
landscape meant that a single crane
306
00:24:54,660 --> 00:24:55,660
would be useless.
307
00:24:56,720 --> 00:25:03,260
So instead of putting the crane down
here, Schwitzer put it up there.
308
00:25:06,440 --> 00:25:11,080
Schwitzer's cunning solution was to use
a deck -mounted erection traveler crane,
309
00:25:11,260 --> 00:25:16,880
an enormous mobile gantry that traveled
along the track on top of the bridge.
310
00:25:18,840 --> 00:25:22,520
Agnes is inspecting a scaled -down model
of Schwitzer's design.
311
00:25:24,270 --> 00:25:29,450
It doesn't really look much like a
crane. It looks more like a house on
312
00:25:29,830 --> 00:25:36,070
The giant shed at the back housed not
only the engines to move the crane along
313
00:25:36,070 --> 00:25:41,170
the tracks, but also six hoisting
engines that operated the jib arm.
314
00:25:41,590 --> 00:25:46,410
This is such a cool piece of
engineering. You don't really see
315
00:25:46,410 --> 00:25:47,410
this anymore.
316
00:25:50,430 --> 00:25:53,070
Standing almost 65 feet tall.
317
00:25:53,320 --> 00:25:58,300
the 350 -ton Erection Traveler crane
rode on the external walls of the
318
00:25:58,720 --> 00:26:03,620
allowing wagons to travel on the rails
underneath the engine room to deliver
319
00:26:03,620 --> 00:26:05,380
materials to the boom at the front.
320
00:26:06,140 --> 00:26:11,440
And with 10 miles of cabling swinging
components into place, the Erection
321
00:26:11,440 --> 00:26:15,580
Traveler built its own platform to
migrate onto as the bridge deck grew.
322
00:26:19,180 --> 00:26:24,690
By shifting forward one piece at a time,
Workers reached the West Bank in 10
323
00:26:24,690 --> 00:26:25,690
months.
324
00:26:29,590 --> 00:26:35,090
A century later, the Lethbridge Viaduct
still carries enormous trains weighing
325
00:26:35,090 --> 00:26:36,210
thousands of tons.
326
00:26:37,770 --> 00:26:43,250
Without the erection traveler crane,
this viaduct and the robust connection
327
00:26:43,250 --> 00:26:46,250
between Alberta and British Columbia
wouldn't exist.
328
00:26:46,550 --> 00:26:48,890
What a remarkable piece of engineering.
329
00:26:59,660 --> 00:27:04,920
To build the longest triple tower cable
stay bridge of all time, the team behind
330
00:27:04,920 --> 00:27:09,540
the Queensferry Crossing will need to
take Schwitzer's revolutionary concept
331
00:27:09,540 --> 00:27:10,620
supersize it.
332
00:27:13,060 --> 00:27:17,560
Over a hundred years after John Edward
Schwitzer pioneered the erection
333
00:27:17,560 --> 00:27:22,820
crane to do heavy lifts in difficult
locations, the concept has been crucial
334
00:27:22,820 --> 00:27:23,820
big construction.
335
00:27:24,740 --> 00:27:29,160
For the Queensferry Crossing, the
longest structure of its kind ever
336
00:27:29,610 --> 00:27:33,830
Scotland's engineers have created a
system that Schwitzer could have only
337
00:27:33,830 --> 00:27:34,830
dreamed of.
338
00:27:39,030 --> 00:27:44,370
With not one, but six erection traveler
cranes, or in this case, gantries.
339
00:27:45,650 --> 00:27:51,670
Lifting 770 ton deck units from floating
barges and progressing forward as the
340
00:27:51,670 --> 00:27:52,670
structure grew.
341
00:27:59,470 --> 00:28:01,510
Breaking another world record.
342
00:28:07,550 --> 00:28:11,730
Until the giant balancing act was sealed
together to become a secured
343
00:28:11,730 --> 00:28:12,730
superstructure.
344
00:28:17,770 --> 00:28:21,630
Their engineering secrets are now only
found deep within.
345
00:28:23,270 --> 00:28:25,410
This is the joints between two segments.
346
00:28:26,460 --> 00:28:32,280
This is the front edge of the already
erected deck, and the front foot of the
347
00:28:32,280 --> 00:28:38,180
gantry needed to be stressed down to all
of this stiffening here, ready to lift
348
00:28:38,180 --> 00:28:41,260
up the 700 tonnes in front of it.
349
00:28:41,960 --> 00:28:46,340
The segment would have been drawn
together, and then if we look up here,
350
00:28:46,340 --> 00:28:51,840
see that there's a metre -wide strip of
concrete that gets cast between the two
351
00:28:51,840 --> 00:28:55,180
segments and joins the two segments
together.
352
00:29:00,360 --> 00:29:05,780
With the cutting -edge iteration of the
erection traveler crane, engineers have
353
00:29:05,780 --> 00:29:07,000
created a masterpiece.
354
00:29:11,060 --> 00:29:16,940
The lifting of these 700 -ton segments
with lifting gantries was a hugely
355
00:29:16,940 --> 00:29:22,000
innovative piece of construction
engineering, a development, actually, of
356
00:29:22,000 --> 00:29:26,420
lifting gantry technology that has been
around for centuries.
357
00:29:33,870 --> 00:29:38,410
But keeping Queensferry Crossing's
enormous mile -and -a -half -long
358
00:29:38,410 --> 00:29:43,270
in the air once the gantries are gone
requires a colossal cable stay system.
359
00:29:45,770 --> 00:29:49,930
But this extremely slender bridge hangs
delicately over the sea.
360
00:29:51,350 --> 00:29:55,570
And a conventional cable arrangement
could not provide sufficient support.
361
00:29:59,690 --> 00:30:02,450
As you see, it's a very elegant, slender
structure.
362
00:30:03,389 --> 00:30:07,650
But if there was a traffic jam and all
the traffic backed up, there would be
363
00:30:07,650 --> 00:30:11,610
this weight on one side and none on the
other, and the deck on the other side
364
00:30:11,610 --> 00:30:15,470
would lift up, and the deck on the
loading side would go down.
365
00:30:20,070 --> 00:30:24,410
This long, slim deck profile needs
additional support to stay standing.
366
00:30:26,300 --> 00:30:31,100
If you don't provide that stiffness, the
structure cannot resist the load on one
367
00:30:31,100 --> 00:30:33,640
side and would fall down under these
asymmetric loadings.
368
00:30:34,140 --> 00:30:38,760
To find a way to stiffen the bridge
deck, inspiration can be found with the
369
00:30:38,760 --> 00:30:40,040
innovators of the past.
370
00:30:50,240 --> 00:30:52,720
Straddling the border between France and
Spain.
371
00:30:54,320 --> 00:30:59,000
are over 200 miles of deep precipices
and deep ravines.
372
00:31:01,220 --> 00:31:02,300
Marvellous journey.
373
00:31:03,200 --> 00:31:04,320
So beautiful.
374
00:31:05,360 --> 00:31:10,940
On the French side of the Pyrenees
mountain range, civil engineer Claude
375
00:31:10,940 --> 00:31:14,120
is hunting down a relic from the golden
age of train travel.
376
00:31:19,790 --> 00:31:24,570
20th century, the most efficient way to
connect this region was by rail.
377
00:31:25,050 --> 00:31:32,050
To cross the Tet River, the gorge was
very deep and Stonebridge would have
378
00:31:32,050 --> 00:31:34,550
taken a lot of time, a lot of money.
379
00:31:35,610 --> 00:31:40,610
The suspension bridge is also a
marvelous structure, but it's not
380
00:31:40,610 --> 00:31:41,610
for railway.
381
00:31:41,630 --> 00:31:47,330
The train is a very heavy loader. And
when the train enters the bridge, it
382
00:31:47,330 --> 00:31:49,580
creates a huge deflection of the
structure.
383
00:31:50,880 --> 00:31:54,680
Like the Queensferry crossing bridge, it
was going to need special
384
00:31:54,680 --> 00:31:55,680
reinforcement.
385
00:32:00,660 --> 00:32:06,580
In 1900, French military engineer Albert
Gisclar patented a clever system
386
00:32:06,580 --> 00:32:11,340
that enabled him to build a bridge in a
brand new way.
387
00:32:13,100 --> 00:32:14,660
I can see it now.
388
00:32:14,960 --> 00:32:16,560
It's just after this curve.
389
00:32:20,720 --> 00:32:23,000
This is the Ponzi Sklar.
390
00:32:25,400 --> 00:32:26,800
And there we are.
391
00:32:27,920 --> 00:32:30,380
A cable -supported railroad crossing.
392
00:32:31,900 --> 00:32:34,980
It's not a standard suspension bridge.
393
00:32:35,300 --> 00:32:36,780
Look at the cross cable.
394
00:32:38,460 --> 00:32:40,760
There, in the middle of the structure.
395
00:32:42,460 --> 00:32:43,900
It's so impressive.
396
00:32:44,460 --> 00:32:46,440
It's a really elegant structure.
397
00:32:49,260 --> 00:32:50,260
Very clever.
398
00:32:53,080 --> 00:32:56,340
Hanging 260 feet over the valley below.
399
00:32:56,880 --> 00:33:01,160
It's the oldest cross -cable railroad
suspension bridge in existence.
400
00:33:03,820 --> 00:33:08,480
And the innovative engineering that
keeps it standing over 100 years later.
401
00:33:08,760 --> 00:33:12,580
You can see the fantastic and clever
cable arrangement.
402
00:33:12,920 --> 00:33:14,920
It's something very, very special.
403
00:33:16,490 --> 00:33:21,090
could be the key to holding the
Queensferry crossing bridge steady for
404
00:33:21,090 --> 00:33:22,090
to come.
405
00:33:25,350 --> 00:33:30,230
Civil engineer Claude Lecaire is
investigating the brilliant design
406
00:33:30,230 --> 00:33:34,950
Pont Gisclar, the oldest cross -cable
railroad suspension bridge in the world.
407
00:33:36,330 --> 00:33:37,330
Oh, wow.
408
00:33:37,630 --> 00:33:39,050
What a great view from here.
409
00:33:39,580 --> 00:33:43,820
It's impossible to see it when you are
in the train, but from this point of
410
00:33:43,820 --> 00:33:48,680
view, you can see the fantastic and
clever cable arrangement. It's something
411
00:33:48,680 --> 00:33:49,960
very, very special.
412
00:33:50,320 --> 00:33:55,780
There is no single suspension cable.
There is two suspension that cross in
413
00:33:55,780 --> 00:34:00,540
middle of the bridge, and that makes all
the suspension system very stiff.
414
00:34:01,880 --> 00:34:04,480
Weighing only 873 tons.
415
00:34:04,920 --> 00:34:11,620
This seemingly fragile structure stands
strong after 110 years, thanks to
416
00:34:11,620 --> 00:34:14,400
Gisclar's ingenious reinforcement
concept.
417
00:34:16,560 --> 00:34:20,900
A traditional suspension bridge has a
pair of cables strung across the
418
00:34:20,900 --> 00:34:24,560
supporting towers and vertical wires
that hold the deck up.
419
00:34:25,920 --> 00:34:31,139
But when a heavy load like a train
enters or leaves one side of the bridge,
420
00:34:31,139 --> 00:34:35,620
imbalanced heavy weight could cause
disastrous deflections in the deck,
421
00:34:35,620 --> 00:34:37,480
the structure in the wrong direction.
422
00:34:39,840 --> 00:34:44,500
Gisclar solved this by continuing the
cables from each tower across to the
423
00:34:44,500 --> 00:34:47,280
at the opposite side, crossing them in
the middle.
424
00:34:48,980 --> 00:34:54,179
Now the heavy load is shared across the
intersecting cables to both solid ground
425
00:34:54,179 --> 00:34:55,179
abutments.
426
00:34:55,820 --> 00:35:00,500
And with the complex web of cables
creating triangular truss -like
427
00:35:00,760 --> 00:35:03,400
even more stiffness is introduced into
the deck.
428
00:35:05,300 --> 00:35:06,680
Here comes the train.
429
00:35:07,460 --> 00:35:13,220
As the train enters the bridge, the
heavy gravity load on that side is
430
00:35:13,220 --> 00:35:15,880
by both sides and both pylons.
431
00:35:17,420 --> 00:35:19,220
This cloud idea was really brilliant.
432
00:35:20,080 --> 00:35:22,540
It's a very innovative idea.
433
00:35:26,800 --> 00:35:31,880
Although many had attempted traditional
suspension bridges for railroads, none
434
00:35:31,880 --> 00:35:35,920
had the strength and stiffness to stand
the test of time, quite like the Pont
435
00:35:35,920 --> 00:35:36,920
Gisclar.
436
00:35:40,200 --> 00:35:42,840
This bridge is a really great design.
437
00:35:43,100 --> 00:35:45,080
It's an inspiration for engineers today.
438
00:35:57,390 --> 00:36:03,990
In Scotland, engineers have built a
cross cable system on a colossal scale.
439
00:36:08,690 --> 00:36:14,590
Enhancing structural strength and depth
for a super long, super slim deck
440
00:36:14,590 --> 00:36:15,590
profile.
441
00:36:24,220 --> 00:36:28,660
The height of where those cables
intersect at their very highest is the
442
00:36:28,660 --> 00:36:29,660
depth of structure.
443
00:36:30,340 --> 00:36:32,380
If you haven't load on one fan,
444
00:36:33,120 --> 00:36:35,580
these stays here will be delivering this
load here.
445
00:36:36,100 --> 00:36:41,480
And these stays coming down from the
north tower will actually act to
446
00:36:41,480 --> 00:36:46,520
load from the fast fan all the way back
to terra firma.
447
00:36:49,100 --> 00:36:52,180
Where the conventional cable stay method
would have failed.
448
00:36:53,070 --> 00:36:58,110
The team opted to extend their cable
stays further, crossing at mid -span,
449
00:36:58,270 --> 00:37:04,210
allowing the force of uneven weight
loading to be transferred all the way
450
00:37:04,210 --> 00:37:06,910
the intersecting cables to the opposite
abutment.
451
00:37:12,210 --> 00:37:15,690
Introduction of additional stiffness
through an overlapping stay system.
452
00:37:15,930 --> 00:37:20,170
This is the first time it's been done on
a cable stay bridge of this scale.
453
00:37:23,880 --> 00:37:29,560
At over 1 ,300 feet, these cables are
some of the longest in the world.
454
00:37:32,300 --> 00:37:39,160
When they inevitably need repairs, the
team has a remarkable
455
00:37:39,160 --> 00:37:40,200
system in place.
456
00:37:41,160 --> 00:37:44,640
Here's a good view of a cable anchorage.
457
00:37:44,840 --> 00:37:49,640
You can actually just see the strands
disappearing through a hole in the deck,
458
00:37:49,680 --> 00:37:53,920
and each of those strands is
individually anchored so that you can
459
00:37:53,920 --> 00:37:54,920
and remove it.
460
00:37:58,660 --> 00:38:03,400
Inside each cable are between 50 and 100
strands of woven wire.
461
00:38:05,450 --> 00:38:10,230
which from under the deck can each be
pulled out and re -threaded without
462
00:38:10,230 --> 00:38:12,510
disrupting the other strands in the
cable.
463
00:38:20,430 --> 00:38:24,930
The replacement of individual cables
with minimum disruption to traffic was a
464
00:38:24,930 --> 00:38:25,970
fundamental requirement.
465
00:38:30,700 --> 00:38:34,760
But maintenance work isn't the only
thing that can bring traffic to a
466
00:38:34,760 --> 00:38:37,560
halt. Mother Nature can, too.
467
00:38:38,600 --> 00:38:42,840
For the Queensferry Crossing Bridge to
withstand Scotland's dramatic natural
468
00:38:42,840 --> 00:38:46,660
forces, the team needs to engineer one
last solution.
469
00:38:49,320 --> 00:38:53,440
The Queensferry Bridge Crossing is a
remarkable engineering achievement.
470
00:38:53,960 --> 00:38:58,820
The team has designed the longest three
-tower cable stay bridge structure in
471
00:38:58,820 --> 00:38:59,669
the world.
472
00:38:59,670 --> 00:39:03,710
But to ensure the structure remains safe
and stable, they must account for
473
00:39:03,710 --> 00:39:05,330
Scotland's extreme weather.
474
00:39:06,790 --> 00:39:09,370
As you can see from the site, it's a
very open environment.
475
00:39:09,610 --> 00:39:12,130
We're very close to the sea and very
exposed to the wind.
476
00:39:12,430 --> 00:39:14,730
The wind speeds can get up to 120 miles
an hour.
477
00:39:15,270 --> 00:39:19,650
On the bridge, these high rectangular
vehicles, they just act like a trail and
478
00:39:19,650 --> 00:39:21,610
they have the same impact as the wind
has on a yacht.
479
00:39:26,700 --> 00:39:31,660
On the old road bridge, gale force winds
had such power that the structure could
480
00:39:31,660 --> 00:39:33,260
violently ripple and swell.
481
00:39:33,940 --> 00:39:38,080
And the ferocious gust could even tip
over high -sided trucks.
482
00:39:39,300 --> 00:39:44,280
For the safety of drivers and residents
living on the banks below, bridge
483
00:39:44,280 --> 00:39:45,540
closures were essential.
484
00:39:48,660 --> 00:39:52,820
But the engineers of the Queens Ferry
Crossing have a solution for that.
485
00:39:55,310 --> 00:39:59,610
So the solution they came up with was a
six Louvre wind bar, which basically
486
00:39:59,610 --> 00:40:04,810
deflects the wind over the top of the
road and protects the vehicles from the
487
00:40:04,810 --> 00:40:09,990
wind. The bottom two Louvres are this
way round, which allows the wind to come
488
00:40:09,990 --> 00:40:14,750
in and start to fade over the top. As
you go up, higher up, then the wind has
489
00:40:14,750 --> 00:40:16,370
helped to take over the traffic.
490
00:40:16,670 --> 00:40:20,490
It's fantastic because it's allowing the
traffic to move uninterrupted at all
491
00:40:20,490 --> 00:40:21,490
times of the year.
492
00:40:21,530 --> 00:40:24,950
Since the bridge opened, over that
period, if we were still on the 4th Road
493
00:40:24,950 --> 00:40:28,090
Bridge, the bridge would have been shut
86 times to traffic.
494
00:40:28,730 --> 00:40:31,690
It's a genius solution to allow the
traffic to keep moving.
495
00:40:33,390 --> 00:40:35,190
It's a phenomenal piece of engineering.
496
00:40:43,330 --> 00:40:46,090
For the team behind this daring project.
497
00:40:49,000 --> 00:40:51,520
The sense of achievement is
immeasurable.
498
00:40:53,720 --> 00:40:57,380
It's an incredible feeling knowing that
you're part of one of the key pieces of
499
00:40:57,380 --> 00:40:58,620
infrastructure in the UK.
500
00:41:01,600 --> 00:41:05,980
Really, there are none like the Queen
Street Crossing in terms of its scale
501
00:41:05,980 --> 00:41:06,980
significance.
502
00:41:11,020 --> 00:41:17,080
By building on the work of the pioneers
of the past, overcoming huge challenges,
503
00:41:18,160 --> 00:41:20,500
and pushing the boundaries of
innovation.
504
00:41:21,640 --> 00:41:26,360
I think if you're a civil engineer and a
project like this doesn't excite you,
505
00:41:26,420 --> 00:41:27,580
you're probably in the wrong game.
506
00:41:28,200 --> 00:41:31,600
It's a groundbreaking project. It's just
an immense engineering achievement.
507
00:41:32,740 --> 00:41:37,580
Engineers are succeeding in making the
impossible possible.
508
00:41:38,360 --> 00:41:40,420
There was a lot of challenging days out
there.
509
00:41:40,660 --> 00:41:41,980
We worked 24 hours a day.
510
00:41:43,690 --> 00:41:47,350
The outcome is a phenomenal bridge and
it's recognised across the world.
511
00:41:47,570 --> 00:41:50,730
There's no doubt the Queen's Ferry
Crossing provides a lifeline for
512
00:41:50,780 --> 00:41:55,330
Repair and Synchronization by
Easy Subtitles Synchronizer 1.0.0.0
48355
Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.