All language subtitles for 8. Example – Critical Path With Float

af Afrikaans
sq Albanian
am Amharic
ar Arabic Download
hy Armenian
az Azerbaijani
eu Basque
be Belarusian
bn Bengali
bs Bosnian
bg Bulgarian
ca Catalan
ceb Cebuano
ny Chichewa
zh-CN Chinese (Simplified)
zh-TW Chinese (Traditional)
co Corsican
hr Croatian
cs Czech
da Danish
nl Dutch
en English
eo Esperanto
et Estonian
tl Filipino
fi Finnish
fr French
fy Frisian
gl Galician
ka Georgian
de German
el Greek
gu Gujarati
ht Haitian Creole
ha Hausa
haw Hawaiian
iw Hebrew
hi Hindi
hmn Hmong
hu Hungarian
is Icelandic
ig Igbo
id Indonesian
ga Irish
it Italian
ja Japanese
jw Javanese
kn Kannada
kk Kazakh
km Khmer
ko Korean
ku Kurdish (Kurmanji)
ky Kyrgyz
lo Lao
la Latin
lv Latvian
lt Lithuanian
lb Luxembourgish
mk Macedonian
mg Malagasy
ms Malay
ml Malayalam
mt Maltese
mi Maori
mr Marathi
mn Mongolian
my Myanmar (Burmese)
ne Nepali
no Norwegian
ps Pashto
fa Persian
pl Polish
pt Portuguese
pa Punjabi
ro Romanian
ru Russian
sm Samoan
gd Scots Gaelic
sr Serbian
st Sesotho
sn Shona
sd Sindhi
si Sinhala
sk Slovak
sl Slovenian
so Somali
es Spanish
su Sundanese
sw Swahili
sv Swedish
tg Tajik
ta Tamil
te Telugu
th Thai
tr Turkish
uk Ukrainian
ur Urdu
uz Uzbek
vi Vietnamese
cy Welsh
xh Xhosa
yi Yiddish
yo Yoruba
zu Zulu
or Odia (Oriya)
rw Kinyarwanda
tk Turkmen
tt Tatar
ug Uyghur
Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated: 1 1 00:00:01,330 --> 00:00:03,312 Here's the project with the float calculated 2 2 00:00:03,312 --> 00:00:05,395 for all the deliverables. 3 3 00:00:06,660 --> 00:00:08,628 The float tells you how much 4 4 00:00:08,628 --> 00:00:10,687 each deliverable can be delayed, 5 5 00:00:10,687 --> 00:00:12,649 or float forward in the schedule, 6 6 00:00:12,649 --> 00:00:16,689 before it would become critical and push out the end date. 7 7 00:00:16,689 --> 00:00:19,457 We calculate it by subtracting the earliest finish 8 8 00:00:19,457 --> 00:00:21,769 from the latest finish of each deliverable, 9 9 00:00:21,769 --> 00:00:25,281 and see how much difference there is. 10 10 00:00:25,281 --> 00:00:28,921 When the latest finish and earliest finish are the same, 11 11 00:00:28,921 --> 00:00:31,269 the deliverable will have zero float, 12 12 00:00:31,269 --> 00:00:33,309 and can't be even one day late 13 13 00:00:33,309 --> 00:00:35,590 without pushing out the deliverables in front of it 14 14 00:00:35,590 --> 00:00:37,558 and thereby extending the end date, 15 15 00:00:37,558 --> 00:00:41,288 which means it's on the critical path. 16 16 00:00:41,288 --> 00:00:44,316 Let's look at some of the deliverables. 17 17 00:00:44,316 --> 00:00:47,520 The Kickoff Meeting float is its latest finish of one 18 18 00:00:47,520 --> 00:00:50,640 minus its earliest finish of one, or zero, 19 19 00:00:50,640 --> 00:00:53,960 which we write on top of the deliverable. 20 20 00:00:53,960 --> 00:00:56,279 All the rest of the deliverables outlined in red 21 21 00:00:56,279 --> 00:01:00,090 also have the same earliest finish and latest finish, 22 22 00:01:00,090 --> 00:01:04,828 and so a float of zero, defining the critical path. 23 23 00:01:04,828 --> 00:01:07,790 If any of these deliverables delay even a day, 24 24 00:01:07,790 --> 00:01:10,162 they will push out the deliverables after it, 25 25 00:01:10,162 --> 00:01:13,301 and the end date will move out. 26 26 00:01:13,301 --> 00:01:17,311 This is the set of deliverables without any schedule slack, 27 27 00:01:17,311 --> 00:01:19,299 where the project manager needs to focus 28 28 00:01:19,299 --> 00:01:21,299 most of their attention. 29 29 00:01:22,353 --> 00:01:26,645 On the other hand, look at the New Floor Plan 1st Draft. 30 30 00:01:26,645 --> 00:01:30,134 The earliest it can finish, if all goes according to plan, 31 31 00:01:30,134 --> 00:01:31,134 is day five. 32 32 00:01:31,974 --> 00:01:34,145 But the latest it could finish, if it had issues, 33 33 00:01:34,145 --> 00:01:36,145 would be day 11. 34 34 00:01:36,145 --> 00:01:40,484 So it has a float of 11 minus five, or six days. 35 35 00:01:40,484 --> 00:01:43,044 And it only has four days of work. 36 36 00:01:43,044 --> 00:01:46,152 That tells the project manager it could be done twice over, 37 37 00:01:46,152 --> 00:01:49,124 and still have two days to spare. 38 38 00:01:49,124 --> 00:01:52,103 In other words, there is not a lot of schedule risk 39 39 00:01:52,103 --> 00:01:55,304 with the New Floor Plan 1st Draft deliverable. 40 40 00:01:55,304 --> 00:01:57,343 The project manager won't ignore it, 41 41 00:01:57,343 --> 00:02:00,003 but will focus most of their attention on the other, 42 42 00:02:00,003 --> 00:02:02,253 critical path deliverables. 43 43 00:02:03,803 --> 00:02:06,783 Similarly, the New Floor Plan 2nd Draft can finish 44 44 00:02:06,783 --> 00:02:10,090 as early as day 15, or as late as day 22, 45 45 00:02:10,090 --> 00:02:11,992 for a float of seven. 46 46 00:02:11,992 --> 00:02:14,504 And they only have three days of work. 47 47 00:02:14,504 --> 00:02:17,613 They could do it three times over, and have a day to spare, 48 48 00:02:17,613 --> 00:02:20,933 before it's needed for the executive approval. 49 49 00:02:20,933 --> 00:02:22,100 Very low risk. 50 50 00:02:23,914 --> 00:02:28,094 Along the bottom, the Training Plan has 16 days of float, 51 51 00:02:28,094 --> 00:02:30,002 with only one day of work, 52 52 00:02:30,002 --> 00:02:32,707 and so there's almost no chance delays on this deliverable 53 53 00:02:32,707 --> 00:02:36,124 will impact the overall project schedule. 54 54 00:02:36,970 --> 00:02:39,641 The critical path is gold to know. 55 55 00:02:39,641 --> 00:02:41,791 It makes the project manager's schedule management job 56 56 00:02:41,791 --> 00:02:44,624 as focused and simple as possible. 57 57 00:02:45,778 --> 00:02:48,290 And now, you understand it better than most, 58 58 00:02:48,290 --> 00:02:51,610 and know exactly how the Gantt chart software calculates it 59 59 00:02:51,610 --> 00:02:52,860 under the hood. 60 60 00:02:54,250 --> 00:02:56,080 And here's the important part. 61 61 00:02:56,080 --> 00:02:58,510 The critical path should be managed closely, 62 62 00:02:58,510 --> 00:03:01,819 even when the stakeholders are not concerned about schedule 63 63 00:03:01,819 --> 00:03:06,138 since any delays drive increases in schedule, cost, 64 64 00:03:06,138 --> 00:03:08,397 as well as brand new risks 65 65 00:03:08,397 --> 00:03:11,468 as the world starts to change under your feet. 66 66 00:03:11,468 --> 00:03:13,248 You want the team to have fun, 67 67 00:03:13,248 --> 00:03:17,187 and don't want to work overtime unless absolutely necessary. 68 68 00:03:17,187 --> 00:03:20,209 But you also want to watch the critical path like a hawk, 69 69 00:03:20,209 --> 00:03:25,126 and get the project finished as soon as it possibly can be. 6140

Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.