Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated:
1
1
00:00:01,330 --> 00:00:03,312
Here's the project with the float calculated
2
2
00:00:03,312 --> 00:00:05,395
for all the deliverables.
3
3
00:00:06,660 --> 00:00:08,628
The float tells you how much
4
4
00:00:08,628 --> 00:00:10,687
each deliverable can be delayed,
5
5
00:00:10,687 --> 00:00:12,649
or float forward in the schedule,
6
6
00:00:12,649 --> 00:00:16,689
before it would become critical and push out the end date.
7
7
00:00:16,689 --> 00:00:19,457
We calculate it by subtracting the earliest finish
8
8
00:00:19,457 --> 00:00:21,769
from the latest finish of each deliverable,
9
9
00:00:21,769 --> 00:00:25,281
and see how much difference there is.
10
10
00:00:25,281 --> 00:00:28,921
When the latest finish and earliest finish are the same,
11
11
00:00:28,921 --> 00:00:31,269
the deliverable will have zero float,
12
12
00:00:31,269 --> 00:00:33,309
and can't be even one day late
13
13
00:00:33,309 --> 00:00:35,590
without pushing out the deliverables in front of it
14
14
00:00:35,590 --> 00:00:37,558
and thereby extending the end date,
15
15
00:00:37,558 --> 00:00:41,288
which means it's on the critical path.
16
16
00:00:41,288 --> 00:00:44,316
Let's look at some of the deliverables.
17
17
00:00:44,316 --> 00:00:47,520
The Kickoff Meeting float is its latest finish of one
18
18
00:00:47,520 --> 00:00:50,640
minus its earliest finish of one, or zero,
19
19
00:00:50,640 --> 00:00:53,960
which we write on top of the deliverable.
20
20
00:00:53,960 --> 00:00:56,279
All the rest of the deliverables outlined in red
21
21
00:00:56,279 --> 00:01:00,090
also have the same earliest finish and latest finish,
22
22
00:01:00,090 --> 00:01:04,828
and so a float of zero, defining the critical path.
23
23
00:01:04,828 --> 00:01:07,790
If any of these deliverables delay even a day,
24
24
00:01:07,790 --> 00:01:10,162
they will push out the deliverables after it,
25
25
00:01:10,162 --> 00:01:13,301
and the end date will move out.
26
26
00:01:13,301 --> 00:01:17,311
This is the set of deliverables without any schedule slack,
27
27
00:01:17,311 --> 00:01:19,299
where the project manager needs to focus
28
28
00:01:19,299 --> 00:01:21,299
most of their attention.
29
29
00:01:22,353 --> 00:01:26,645
On the other hand, look at the New Floor Plan 1st Draft.
30
30
00:01:26,645 --> 00:01:30,134
The earliest it can finish, if all goes according to plan,
31
31
00:01:30,134 --> 00:01:31,134
is day five.
32
32
00:01:31,974 --> 00:01:34,145
But the latest it could finish, if it had issues,
33
33
00:01:34,145 --> 00:01:36,145
would be day 11.
34
34
00:01:36,145 --> 00:01:40,484
So it has a float of 11 minus five, or six days.
35
35
00:01:40,484 --> 00:01:43,044
And it only has four days of work.
36
36
00:01:43,044 --> 00:01:46,152
That tells the project manager it could be done twice over,
37
37
00:01:46,152 --> 00:01:49,124
and still have two days to spare.
38
38
00:01:49,124 --> 00:01:52,103
In other words, there is not a lot of schedule risk
39
39
00:01:52,103 --> 00:01:55,304
with the New Floor Plan 1st Draft deliverable.
40
40
00:01:55,304 --> 00:01:57,343
The project manager won't ignore it,
41
41
00:01:57,343 --> 00:02:00,003
but will focus most of their attention on the other,
42
42
00:02:00,003 --> 00:02:02,253
critical path deliverables.
43
43
00:02:03,803 --> 00:02:06,783
Similarly, the New Floor Plan 2nd Draft can finish
44
44
00:02:06,783 --> 00:02:10,090
as early as day 15, or as late as day 22,
45
45
00:02:10,090 --> 00:02:11,992
for a float of seven.
46
46
00:02:11,992 --> 00:02:14,504
And they only have three days of work.
47
47
00:02:14,504 --> 00:02:17,613
They could do it three times over, and have a day to spare,
48
48
00:02:17,613 --> 00:02:20,933
before it's needed for the executive approval.
49
49
00:02:20,933 --> 00:02:22,100
Very low risk.
50
50
00:02:23,914 --> 00:02:28,094
Along the bottom, the Training Plan has 16 days of float,
51
51
00:02:28,094 --> 00:02:30,002
with only one day of work,
52
52
00:02:30,002 --> 00:02:32,707
and so there's almost no chance delays on this deliverable
53
53
00:02:32,707 --> 00:02:36,124
will impact the overall project schedule.
54
54
00:02:36,970 --> 00:02:39,641
The critical path is gold to know.
55
55
00:02:39,641 --> 00:02:41,791
It makes the project manager's schedule management job
56
56
00:02:41,791 --> 00:02:44,624
as focused and simple as possible.
57
57
00:02:45,778 --> 00:02:48,290
And now, you understand it better than most,
58
58
00:02:48,290 --> 00:02:51,610
and know exactly how the Gantt chart software calculates it
59
59
00:02:51,610 --> 00:02:52,860
under the hood.
60
60
00:02:54,250 --> 00:02:56,080
And here's the important part.
61
61
00:02:56,080 --> 00:02:58,510
The critical path should be managed closely,
62
62
00:02:58,510 --> 00:03:01,819
even when the stakeholders are not concerned about schedule
63
63
00:03:01,819 --> 00:03:06,138
since any delays drive increases in schedule, cost,
64
64
00:03:06,138 --> 00:03:08,397
as well as brand new risks
65
65
00:03:08,397 --> 00:03:11,468
as the world starts to change under your feet.
66
66
00:03:11,468 --> 00:03:13,248
You want the team to have fun,
67
67
00:03:13,248 --> 00:03:17,187
and don't want to work overtime unless absolutely necessary.
68
68
00:03:17,187 --> 00:03:20,209
But you also want to watch the critical path like a hawk,
69
69
00:03:20,209 --> 00:03:25,126
and get the project finished as soon as it possibly can be.
6140
Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.