Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated:
1
1
00:00:00,870 --> 00:00:04,340
The Gantt chart is the formal time baseline.
2
2
00:00:04,340 --> 00:00:06,340
Here's an example of a Gantt chart,
3
3
00:00:06,340 --> 00:00:08,600
for the Department Process Improvement Project,
4
4
00:00:08,600 --> 00:00:11,433
we prepared a WBS and precedence diagram for earlier.
5
5
00:00:12,370 --> 00:00:14,620
The deliverables are mapped to the calendar
6
6
00:00:14,620 --> 00:00:16,260
so that those that take more time,
7
7
00:00:16,260 --> 00:00:18,843
are shown proportionally longer on the chart.
8
8
00:00:20,600 --> 00:00:23,380
The critical path, the back to back path
9
9
00:00:23,380 --> 00:00:26,093
of the longest deliverables is shown in red.
10
10
00:00:27,054 --> 00:00:31,430
The Gantt chart is one to one with the precedence diagram,
11
11
00:00:31,430 --> 00:00:33,493
which we simply loaded into the software.
12
12
00:00:34,680 --> 00:00:36,933
The deliverables are the bars,
13
13
00:00:37,770 --> 00:00:40,113
and the precedence arrows are the links.
14
14
00:00:41,820 --> 00:00:44,360
In one convenient, intuitive chart,
15
15
00:00:44,360 --> 00:00:48,170
we can see the project scope mapped onto the calendar
16
16
00:00:48,170 --> 00:00:50,203
and now know the project end date.
17
17
00:00:52,610 --> 00:00:54,550
And here, on the Gantt chart,
18
18
00:00:54,550 --> 00:00:56,790
is where we add the work packages,
19
19
00:00:56,790 --> 00:00:58,923
indented underneath the deliverables.
20
20
00:01:00,330 --> 00:01:02,150
Remember in the section on deliverables,
21
21
00:01:02,150 --> 00:01:04,150
we noted that work packages,
22
22
00:01:04,150 --> 00:01:06,910
the max two-week subdivisions of longer deliverables
23
23
00:01:06,910 --> 00:01:08,700
used for schedule tracking,
24
24
00:01:08,700 --> 00:01:11,040
don't go on the WBS or precedence diagram
25
25
00:01:11,040 --> 00:01:12,400
since they would make them too large
26
26
00:01:12,400 --> 00:01:14,273
and obscure the deliverable focus.
27
27
00:01:15,270 --> 00:01:18,340
However, they do go on the Gantt chart,
28
28
00:01:18,340 --> 00:01:19,940
since their purpose is to enable
29
29
00:01:19,940 --> 00:01:21,750
later monitoring and control,
30
30
00:01:21,750 --> 00:01:24,823
so you will know the real schedule status every month.
31
31
00:01:26,030 --> 00:01:27,630
All the Gantt chart applications
32
32
00:01:27,630 --> 00:01:29,610
enable you to simply indent the work packages
33
33
00:01:29,610 --> 00:01:32,113
underneath their deliverable for easy management.
34
34
00:01:32,970 --> 00:01:34,840
You can click the minus sign to collapse them
35
35
00:01:34,840 --> 00:01:36,920
if you only want to see the deliverables,
36
36
00:01:36,920 --> 00:01:38,940
and click the plus sign to expand them
37
37
00:01:38,940 --> 00:01:40,690
when you do your monthly statusing.
38
38
00:01:42,450 --> 00:01:45,700
We sometimes also add activities to the Gantt chart,
39
39
00:01:45,700 --> 00:01:48,110
when they have very different resource requirements
40
40
00:01:48,110 --> 00:01:49,810
and we want to record the exact time
41
41
00:01:49,810 --> 00:01:51,160
the resources are required.
42
42
00:01:52,015 --> 00:01:54,150
Later in planning, we will look at using
43
43
00:01:54,150 --> 00:01:56,833
resource usage reports across the calendar.
44
44
00:01:58,330 --> 00:02:00,400
We can indent the activities under the deliverables
45
45
00:02:00,400 --> 00:02:04,373
or work package, and collapse or expand them as needed.
3941
Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.