Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated:
1
1
00:00:01,290 --> 00:00:03,530
Now, let's look at the practical essentials
2
2
00:00:03,530 --> 00:00:07,650
of risk management planning, including the six steps
3
3
00:00:07,650 --> 00:00:09,610
of the formal process,
4
4
00:00:09,610 --> 00:00:12,480
baselining the risk register and budget,
5
5
00:00:12,480 --> 00:00:16,400
allocating the time buffer using critical chain management,
6
6
00:00:16,400 --> 00:00:17,773
and opportunity planning.
7
7
00:00:19,571 --> 00:00:21,220
We have a solid baseline for scope
8
8
00:00:21,220 --> 00:00:25,220
with the work breakdown structure, time with the Gantt chart,
9
9
00:00:25,220 --> 00:00:27,240
and cost with the deliverables roll-up
10
10
00:00:27,240 --> 00:00:29,150
and perhaps a cost curve.
11
11
00:00:29,150 --> 00:00:31,970
Now, we need to be ready for things that might go wrong.
12
12
00:00:32,900 --> 00:00:34,700
And we shouldn't shy away from them.
13
13
00:00:35,550 --> 00:00:38,240
A realistic project plan considers problems
14
14
00:00:38,240 --> 00:00:41,860
that might occur, minimizes them before starting,
15
15
00:00:41,860 --> 00:00:44,310
and reserves time and money to deal with them
16
16
00:00:44,310 --> 00:00:45,503
if they do happen.
17
17
00:00:46,610 --> 00:00:48,210
This risk management planning
18
18
00:00:48,210 --> 00:00:50,320
is one of the greatest advantages
19
19
00:00:50,320 --> 00:00:52,020
of the project management process.
20
20
00:00:53,870 --> 00:00:57,963
First, what is the difference between risks and issues?
21
21
00:00:58,840 --> 00:01:03,060
Risks differ from issues because they are uncertain.
22
22
00:01:03,060 --> 00:01:05,053
They really might not happen.
23
23
00:01:06,340 --> 00:01:09,380
Best practice says risks must have a probability
24
24
00:01:09,380 --> 00:01:11,823
of 80% or less.
25
25
00:01:12,830 --> 00:01:16,060
At 90% and above, there is not enough likelihood
26
26
00:01:16,060 --> 00:01:20,300
of heading them off and they should be treated as issues.
27
27
00:01:20,300 --> 00:01:21,960
You should put the time and the money to deal
28
28
00:01:21,960 --> 00:01:24,760
with them directly in the plan and if they don't happen
29
29
00:01:24,760 --> 00:01:25,823
then you got lucky.
30
30
00:01:26,670 --> 00:01:28,510
You should spend your time on the problems
31
31
00:01:28,510 --> 00:01:31,010
you have a realistic chance of managing
32
32
00:01:31,010 --> 00:01:33,683
with probability 80% or less.
33
33
00:01:35,270 --> 00:01:39,430
Now, for small projects, perhaps under about $20K,
34
34
00:01:39,430 --> 00:01:41,050
you can allocate a risk budget simply
35
35
00:01:41,050 --> 00:01:42,620
by setting aside time and money
36
36
00:01:42,620 --> 00:01:45,360
as a percentage of the rest of the project.
37
37
00:01:45,360 --> 00:01:47,630
Most commonly 15%.
38
38
00:01:47,630 --> 00:01:50,800
For example, for a 40 day $20K project,
39
39
00:01:50,800 --> 00:01:54,913
add 6 days and $3K to the risk budget and move on.
40
40
00:01:56,300 --> 00:01:59,450
For larger projects, it is very worthwile
41
41
00:01:59,450 --> 00:02:01,993
to conduct the full risk planning process.
42
42
00:02:02,960 --> 00:02:05,110
Then you will be able to justify
43
43
00:02:05,110 --> 00:02:06,480
whatever amount of time and money
44
44
00:02:06,480 --> 00:02:08,120
you put in the risk budget.
45
45
00:02:08,120 --> 00:02:12,363
Commonly between five and 15%, but could be more or less.
46
46
00:02:13,200 --> 00:02:16,350
If your project is $10 million, management is unlikely
47
47
00:02:16,350 --> 00:02:18,920
to approve a risk budget of $1.5 million
48
48
00:02:18,920 --> 00:02:22,390
without a good reason, and the risk planning process
49
49
00:02:22,390 --> 00:02:25,650
gives you the information to justify the budget,
50
50
00:02:25,650 --> 00:02:27,203
whatever amount it might be.
51
51
00:02:28,470 --> 00:02:32,230
And second, the process is actually useful,
52
52
00:02:32,230 --> 00:02:35,450
and really can significantly reduce the risks
53
53
00:02:35,450 --> 00:02:37,300
before you start.
54
54
00:02:37,300 --> 00:02:41,983
That is planning is a project improvement exercise.
55
55
00:02:43,580 --> 00:02:46,750
As you go through risk planning and later monitoring
56
56
00:02:46,750 --> 00:02:50,580
and control, remember, in a professional organization,
57
57
00:02:50,580 --> 00:02:52,910
management wants to know the risks.
58
58
00:02:52,910 --> 00:02:55,323
So you should never ever minimize them.
59
59
00:02:56,400 --> 00:02:58,843
Here's a story about how I learned this lesson.
60
60
00:02:59,810 --> 00:03:02,410
Once when I was a fairly junior employee,
61
61
00:03:02,410 --> 00:03:04,780
the president of the company I worked at asked me
62
62
00:03:04,780 --> 00:03:07,493
how risky an idea was that I was proposing.
63
63
00:03:08,620 --> 00:03:11,700
I really liked my idea and wanted to get his support,
64
64
00:03:11,700 --> 00:03:14,753
so made the mistake of saying there was no risk.
65
65
00:03:15,820 --> 00:03:18,190
Several minutes later, he stopped lecturing me
66
66
00:03:18,190 --> 00:03:21,530
about how there was no such thing as no risk.
67
67
00:03:21,530 --> 00:03:24,890
That concept didn't exist in this universe.
68
68
00:03:24,890 --> 00:03:27,710
He wanted to know the risk, and it was my job
69
69
00:03:27,710 --> 00:03:29,570
to tell him the risk.
70
70
00:03:29,570 --> 00:03:30,960
You are putting your job on the line
71
71
00:03:30,960 --> 00:03:33,853
by saying something like that son, et cetera.
72
72
00:03:34,760 --> 00:03:38,633
So I have never said the words no risk again.
73
73
00:03:39,620 --> 00:03:43,430
There might be low risk, there might be manageable risk,
74
74
00:03:43,430 --> 00:03:46,600
but to say something has no risk is a fast way
75
75
00:03:46,600 --> 00:03:49,100
to lose credibility with your listeners about anything
76
76
00:03:49,100 --> 00:03:50,050
you say after that.
77
77
00:03:51,080 --> 00:03:54,030
You want to be as accurate as you can, but if you are going
78
78
00:03:54,030 --> 00:03:56,180
to make a mistake estimating risk,
79
79
00:03:56,180 --> 00:03:58,223
never make it on the low side.
80
80
00:04:00,230 --> 00:04:03,110
Doing a good thorough job on risk planning
81
81
00:04:03,110 --> 00:04:05,690
will go a long way to convincing the stakeholders
82
82
00:04:05,690 --> 00:04:08,913
that the projects is in realistic safe hands.
7224
Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.